17.—(1) Unless otherwise agreed in writing by the MMO in accordance with paragraph (2), no more than eight pin piles for the offshore substation jacket foundation shall be installed between 1 April and 15 May.
(2) The undertaker shall submit a pin pile construction method statement to the MMO for approval showing the proposed numbers of piles to be installed and the estimated piling duration. If approved by the MMO, the installation must be carried out in accordance with the approved pin pile construction method statement.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: