The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Arbitration

20.  Except for differences or disputes arising under paragraph 10(2), 10(4), 11(1), 12(1) to (3) and (5) to (11) and 13(1) to (3) and (5) to (11), any difference or dispute arising between the undertaker and National Grid under this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid, be referred to and determined by arbitration in accordance with article 39 (arbitration).