The Able Marine Energy Park Development Consent Order 2014

Arbitration

This section has no associated Explanatory Memorandum

57.  Any difference under any provision of this Order, unless otherwise provided for, must be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.