44.—(1) No development is to commence until the detailed design of the Regulated Tidal Exchange (“RTE”) sluices has been submitted to and approved by the relevant planning authority, in consultation with the Environment Agency.
(2) The detailed design information must include the size and flow capacity of the sluices within the RTE scheme.
(3) No development is to commence until the detailed design of the channel leaving the Managed Realignment site and the invert level has been submitted to and approved by the relevant planning authority, in consultation with the Environment Agency, to include detailed design drawings, including dimensions.
(4) The discharge channel exiting the realignment site must be no larger than that currently presented and assessed in EX 28.3 Part 3 (11.6 metres bed width (invert level 1.5 metres AOD) with 1V:3H side slopes rising to an edge weir level of 2.0 metres AOD), unless otherwise agreed with the Environment Agency.
(5) The invert level of the drainage channel must be no higher than that currently presented and assessed in EX28.3 Part 3, Final Compensation Proposals, October 2012, (1.5 metres AOD), unless agreed otherwise in writing with the Environment Agency.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: