SCHEDULES

SCHEDULE 8DEEMED MARINE LICENCE

PART 2LICENSED ACTIVITIES

Rock armour

9.  The licence holder is permitted to deposit rock armouring to the northern extent of the flood defence breach at Cherry Cobb Sands under the following conditions—

(a)the quantity of rock to be placed must be agreed with the MMO at least 4 weeks prior to works commencement;

(b)the exact location must be agreed with the MMO at least 4 weeks prior to works commencement; and

(c)the placement of rock armouring must only be carried out in accordance with the agreed location and rock quantity.

Temporary bog matting

10.—(1) The licence holder is permitted to deposit temporary bog matting upon the foreshore at the Cherry Cob Sands site for the purposes of construction plant movement.

(2) The licence holder must ensure the bog matting is removed as soon as practicable once the activities for which they have been deposited have been completed.