SCHEDULES

SCHEDULE 9PROTECTIVE PROVISIONS

PART 1FOR THE PROTECTION OF THE HUMBER CONSERVANCY

Removal of temporary works

11

On completion of the construction of any part of a permanent authorised work, the Harbour Authority must as soon as practicable remove—

a

any temporary tidal work carried out only for the purposes of that part of the permanent work; and

b

any materials, plant and equipment used for such construction,

and must make good the site to the reasonable satisfaction of the Conservancy Authority.