SCHEDULES
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
LAND AT SURFACE LEVEL OF WHICH TEMPORARY POSSESSION MAY NOT BE TAKEN
PART 1 PROTECTION FOR NETWORK RAIL
1.The following provisions of this Part of this Schedule have...
2.In this Part of this Schedule— “construction” includes execution, placing,...
3.(1) Where under this Part of this Schedule Network Rail...
4.(1) LUL must not exercise the powers conferred by article...
5.(1) LUL must, before commencing construction of any specified work,...
7.LUL must— (a) at all times afford reasonable facilities to...
8.Network Rail must at all times afford reasonable facilities to...
9.(1) If any permanent or temporary alterations or additions to...
10.LUL must repay to Network Rail all reasonable fees, costs,...
11.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
12.LUL must not provide any illumination or illuminated sign or...
14.Any additional expenses which Network Rail may reasonably incur in...
15.(1) LUL must pay to Network Rail all reasonable costs,...
PART 2 PROTECTION FOR THE LONDON BOROUGHS OF LAMBETH, SOUTHWARK AND WANDSWORTH
20.(1) The following provisions of this Part of this Schedule...
21.Before commencing to construct any scheduled work LUL must consult...
23.Before commencing to construct any authorised work which will involve...
25.LUL must not, except with the consent of the appropriate...
26.Except in an emergency or where reasonably necessary to secure...
27.LUL must, if reasonably so required by the appropriate Council,...
28.LUL must indemnify the appropriate Council against any claim which...
29.Wherever in this Part of this Schedule provision is made...
PART 3 PROTECTION FOR THE ENVIRONMENT AGENCY
30.(1) The following provisions of this Part of this Schedule...
31.(1) Before beginning to construct any specified work, LUL must...
32.Without limitation on the scope of paragraph 31, the requirements...
33.(1) Subject to sub-paragraph (2), any specified work, and all...
34.(1) Subject to sub-paragraph (5) LUL must from the commencement...
35.Subject to paragraph 37, if by reason of the construction...
37.Nothing in paragraphs 33(4), 34(3), 35, 36(3) and 36(4) authorises...
38.LUL must indemnify the Agency in respect of all costs,...
39.(1) Without affecting the other provisions of this Part of...
41.Any dispute arising between LUL and the Agency under this...
PART 4 PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
PART 5 PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 7 PROTECTION FOR THE MARINE MANAGEMENT ORGANISATION
77.(1) The following provisions of this Part of this Schedule...
78.(1) Before beginning to construct or carry out any specified...
79.Without limitation on the scope of paragraph 78, the requirements...
80.Where any specified work involves dredging, the plans submitted under...
81.(1) Subject to sub-paragraph (2), any specified work must be...
82.Where there is any actual or potential conflict between any...
83.Where there is any actual or potential conflict between any...
85.Any dispute arising between LUL and the MMO under this...