Surface water drainage and water discharge
10.—(1) No stage of the authorised development must commence until, for that stage, details of the surface water drainage system (including means of pollution control) for both temporary and permanent works have been submitted to and approved, in writing, by the relevant planning authority. The details must include copies of and take account of any consultation responses from the Environment Agency.
(2) The surface water drainage system must be constructed in accordance with the approved details except to the extent that a variation to the details is approved by the relevant planning authority in writing. Any submission to vary the approved details must include copies of and take account of any consultation responses from the Environment Agency.
(3) No discharge of water used under article 14 (discharge of water) must be made until written details of the location and rate of discharge have been submitted to and approved, in writing, by the relevant planning authority. The details must include copies of and take account of any consultation responses from the Environment Agency.