Search Legislation

The Hornsea One Offshore Wind Farm Order 2014

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Section 31

 Help about opening options

Alternative versions:

Status:

Point in time view as at 31/12/2014.

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Hornsea One Offshore Wind Farm Order 2014. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Defence to proceedings in respect of statutory nuisanceE+W+S

31.—(1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 1990(1) (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within paragraph (g) of section 79(1) of that Act (noise emitted from premises so as to be prejudicial to health or a nuisance) no order is to be made, and no fine may be imposed, under section 82(2) of that Act if—

(a)the defendant shows that the nuisance—

(i)relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project and that the nuisance is attributable to the carrying out of the authorised project in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction site) or 65 (noise exceeding registered level), of the Control of Pollution Act 1974(2); or

(ii)is a consequence of the construction or maintenance of the authorised project and that it cannot reasonably be avoided; or

(b)the defendant shows that the nuisance is a consequence of the use of the authorised project and that it cannot reasonably be avoided.

(2) Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to consent for registered noise level to be exceeded), do not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project.

Commencement Information

I1Art. 31 in force at 31.12.2014, see art. 1

(1)

1990 c.43. There are amendments to this Act which are not relevant to this Order.

(2)

1974 c.40. Sections 61(9) and 65(8) were amended by section 162 of, and paragraph 15 of Schedule 3 to, the Environmental Protection Act 1990, c.25. There are other amendments to the 1974 Act which are not relevant to this Order.