SCHEDULES

SCHEDULE 12Protective provisions

PART 5For the protection of Associated British Ports

I147

1

Before commencing the construction of the specified works the undertaker must furnish to A. B. Ports for its approval, which it must not unreasonably withhold, plans of the work showing the general mode of construction, depth and method of trenching and possible cable protection; and such works—

a

must not be constructed otherwise than in accordance with such plans as may be approved by A. B. Ports; and

b

are to be executed to the reasonable satisfaction of A. B. Ports.

2

When submitting plans in respect of the specified works to the Secretary of State pursuant to article 39 (certification of plans etc), the undertaker must—

a

send a copy of those plans to A. B. Ports; and

b

on receipt of approval of plans or of any conditions or restrictions imposed by the Secretary of State, send a copy to A. B. Ports.

3

If A. B. Ports fails to express its disapproval of any plans within 56 days after they have been delivered to it under sub-paragraph (1), it is deemed to have approved them.