SCHEDULES

SCHEDULE 8Deemed Marine Licences under the Marine and Coastal Access Act 2009 – Deemed Marine Licence 1

PART 2Licence conditions

Pre-construction plans and documentationI115

1

Each programme, statement, plan, protocol or scheme required to be approved under condition 13—

a

shall be submitted for approval at least four months prior to the intended start of construction, except where otherwise stated or where an alternative date is agreed in writing by the MMO; and

b

shall be accompanied by—

i

a statement confirming that the licence-holder has complied with condition 13(3) in relation to such programme, statement, plan, protocol or scheme; and

ii

any comments received by the licence-holder under condition 13(4), or a statement from the licence-holder confirming that no such comments were received.

2

The licence-holder shall comply with all documents approved under licence condition 13 in carrying out the licensed activities except to the extent agreed in writing by the MMO.

3

Prior to agreeing an alternative date under paragraph (1)(a) or a change to approved details under paragraph (2) relating to any document in respect of which consultation is required under condition 13(6), the MMO must consult with the relevant consultation body referred to in that condition.