- Latest available (Revised)
- Point in Time (01/09/2019)
- Original (As made)
Point in time view as at 01/09/2019.
There are currently no known outstanding effects for the The Single Source Contract Regulations 2014, PART 11.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
57. In this Part, “contracting authority” means the party which is, or would be, liable to pay the contract price under a qualifying sub-contract.
58.—(1) The amount specified for the purposes of section 28(3)(c) and (4)(c) (minimum value of a qualifying sub-contract) is £25,000,000.
(2) A contract may be a contract to which section 28(3) or (4) applies only if it is neither—
(a)made within the framework of an international cooperative defence programme [F1, except where the parties to the contract agree that it is a contract which should be a qualifying sub-contract]; nor
(b)made wholly for the purposes of one or more of the following—
(i)the acquisition of land (including existing buildings or other structures, and land covered with water), and any estate, interest, easement, servitude or right in or over such land;
(ii)the management or maintenance of any land or buildings or other structures; [F2nor]
F3(iii). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
[F4(c)a contract in relation to which compliance with Part 4, 5 or 6 of the Regulations (records and reports), or section 26 of the Act (duty to report relevant events, circumstances and information), would require disclosure of information which the Secretary of State considers would create a risk to national security; nor
(d)a contract falling within sub-paragraph (e) below;
(e)a contract (B) falls within this sub-paragraph if—
(i)B replaced a contract (A),
(ii)the purpose of B is to ensure the performance of contractual obligations which were to be performed under A,
(iii)A was not a qualifying defence contract or qualifying sub-contract,
(iv)at least one of the parties to A is also a party to B,
(v)at least one of the parties to B was not a party to A, and
(vi)B is in all material respects (save for the identity of the parties to the contract) identical to A.]
(3) A contract may be a contract to which section 28(3) applies only if the performance of at least 50% by value of the obligations under the contract is required either—
(a)to enable the primary contractor to perform the qualifying defence contract mentioned in section 28(3)(a); or
(b)to enable the combined performance of the qualifying defence contract mentioned in section 28(3)(a) and any other qualifying defence contracts or qualifying sub-contracts, or prospective qualifying defence contracts or qualifying sub-contracts, to which the primary contractor (or any person associated with the primary contractor) is or might become party.
(4) A contract may be a contract to which section 28(4) applies only if the performance of at least 50% by value of the obligations under the contract is required either—
(a)to enable the performance of contract A (within the meaning of section 28(4)(a)); or
(b)to enable the combined performance of contract A and any other qualifying defence contracts or qualifying sub-contracts, or prospective qualifying defence contracts or qualifying sub-contracts, to which the person for whom anything is to be provided under contract A (or any person associated with that person) is or might become party.
(5) For the purposes of paragraphs (3) and (4), one or more obligations under a contract (“the actual contract”) form 50% by value of the obligations under that contract if, were they to constitute all the obligations under a contract, the value of that contract would be at least 50% of the value of the actual contract.
(6) Part 2 of the Act, and these Regulations, shall not apply to a qualifying sub-contract in respect of which no notice has been given under section 29(2)(b) or (4)(b).
Textual Amendments
F1Words in reg. 58(2)(a) inserted (1.8.2018) by The Single Source Contract (Amendment) Regulations 2018 (S.I. 2018/917), regs. 1, 6(1)
F2Word in reg. 58(2)(b)(ii) substituted (1.8.2018) by The Single Source Contract (Amendment) Regulations 2018 (S.I. 2018/917), regs. 1, 6(2)
F3Reg. 58(2)(b)(iii) omitted (1.8.2018) by virtue of The Single Source Contract (Amendment) Regulations 2018 (S.I. 2018/917), regs. 1, 6(3)
F4Reg. 58(2)(c)-(e) inserted (1.8.2018) by The Single Source Contract (Amendment) Regulations 2018 (S.I. 2018/917), regs. 1, 6(4)
59. For the purposes of section 28, the award of a contract is the result of a competitive process if—
(a)the contracting authority either—
(i)published a notice of intention to seek offers in relation to the provision of goods, works or services; or
(ii)invited one or more persons other than the sub-contractor, and not associated with the sub-contractor, to negotiate or provide offers in relation to the provision of goods, works or services;
(b)the contracting authority conducted a transparent and arms-length procurement process;
(c)the contracting authority used appropriate evaluation criteria to identify the offer made by the sub-contractor as the best offer;
(d)the material terms of the contract are wholly or substantially the same as that best offer; and
(e)at the time of making that offer, the sub-contractor did not consider it likely, or could not reasonably have considered it likely, that its offer would be the only offer reasonably capable of acceptance by the contracting authority.
60.—(1) This regulation applies where the contracting authority—
(a)has either—
(i)published a notice of intention to seek offers in relation to a proposed agreement or other arrangement (“framework agreement”) which establishes terms under which a person (a “[F5framework supplier]”) would enter into one or more contracts with the contracting authority in the period during which the framework agreement applies; or
(ii)invited two or more persons to negotiate or provide offers in relation to the terms of a proposed framework agreement;
(b)has entered into a framework agreement with one or more [F6framework suppliers]; and
(c)enters into a contract with a [F7sub-contractor].
(2) For the purposes of section 28, the award of a contract is the result of a competitive process if—
(a)the terms governing the price payable under the contract are determined by a framework agreement and the conditions in paragraph (3) are met; or
(b)the terms governing the price payable under the contract are determined by a competition between two or more [F6framework suppliers] and the conditions in paragraph (4) are met.
(3) The conditions mentioned in paragraph (2)(a) are—
(a)the procurement process by which the contracting authority entered into the framework agreement with the sub-contractor—
(i)was transparent and arms-length; and
(ii)used appropriate evaluation criteria to determine which [F8person or persons] should be awarded a framework agreement;
(b)the material terms of the framework agreement are wholly or substantially the same as were offered by the sub-contractor—
(i)in a tender submitted in response to the notice mentioned in sub-paragraph (1)(a)(i); or
(ii)in negotiations following the invitation mentioned in sub-paragraph (1)(a)(ii);
(c)at the time of making that offer, the sub-contractor did not consider it likely, or could not have reasonably considered it likely, that its offer would be the only offer reasonably capable of acceptance by the contracting authority; and
(d)where this regulation applies by virtue of paragraph (1)(a)(ii), the persons mentioned in that paragraph included at least one person who was not the sub-contractor (or a person associated with the sub-contractor).
(4) The conditions mentioned in paragraph (2)(b) are—
(a)at least one of those [F6framework suppliers] was not the sub-contractor (or a person associated with the sub-contractor);
(b)the competition—
(i)was transparent and arms-length; and
(ii)used appropriate evaluation criteria to identify the offer made by the sub-contractor as the best offer;
(c)the terms governing the price payable under the contract are wholly or substantially the same as were offered by the sub-contractor in that best offer; and
(d)at the time of making that offer, the sub-contractor did not consider it likely, or could not have reasonably considered it likely, that its offer in respect of the contract would be the only offer reasonably capable of acceptance by the contracting authority.
Textual Amendments
F5Words in reg. 60(1)(a) substituted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 18(3)
F6Words in reg. 60 substituted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 18(2)
F7Word in reg. 60(1)(c) substituted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 18(4)
F8Words in reg. 60(3)(a)(ii) substituted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 18(5)
61.—(1) Where either—
(a)a primary contractor (“A”) proposes to enter into a contract with another person (“B”), and the proposed contract involves the provision by B of anything for the purposes of a qualifying defence contract to which A is a party, or
(b)a person (“C”) proposes to enter into a contract with another person (“D”), and the proposed contract involves the provision by D of anything for the purposes of a qualifying sub-contract to which C is a party,
A or C (as the case may be) must assess whether the proposed contract would be a qualifying sub-contract if it were entered into.
(2) A or C (as the case may be) must keep a record of the assessment for the purpose of its inclusion in the records which A or C (as the case may be) would be required by regulation 20 to keep if the contract were entered into.
(3) Where the assessment is that the proposed contract would be a qualifying sub-contract if it were entered into, A or C (as the case may be) must give notice in writing of that fact to the Secretary of State and to B or D (as the case may be).
(4) Where—
(a)a person (“E”) proposes to enter into a qualifying defence contract or a qualifying sub-contract (“the proposed contract”),
(b)E also proposes to enter into a contract (“the proposed sub-contract”) with another person (“F”), and
(c)the proposed sub-contract involves the provision by F of anything for the purposes of the proposed contract,
E must assess whether the proposed sub-contract would be a qualifying sub-contract if it and the proposed contract were entered into.
(5) E must keep a record of the assessment for the purpose of its inclusion in the records which E would be required by regulation 20 to keep if the proposed contracts were entered into.
(6) Where the assessment is that the proposed sub-contract would be a qualifying sub-contract if it were entered into, E must give notice in writing of that fact to the Secretary of State and to F.
[F9(7) For the purposes of paragraphs (2) and (5), where the value of the proposed contract is not less than £15,000,000, the record of the assessment must contain an assessment of whether the proposed contract would be the result of a competitive process and any other reason relied upon to justify a negative assessment.
(8) Where A, C or E (as the case may be) makes a record of assessment, A, C or E must give notice in writing to the Secretary of State and the SSRO that an assessment has been made.]
Textual Amendments
F9Reg. 61(7)(8) inserted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 19
62.—(1) Where an assessment is made under regulation 61(1) that a proposed contract would be a qualifying sub-contract if it were entered into, B or D (as the case may be) may appeal to the SSRO against the assessment.
(2) Where an assessment is made under regulation 61(4) that a proposed sub-contract would be a qualifying sub-contract if it and the proposed contract were entered into, F may appeal to the SSRO against the assessment.
(3) No appeal may be brought—
(a)under paragraph (1) after the proposed contract is entered into;
(b)under paragraph (2) after the proposed sub-contract is entered into.
(4) An appeal must be commenced by a written notice (“notice of appeal”) containing the following information—
(a)the name and contact details of the person bringing the appeal;
(b)if the person bringing the appeal is a company, its registered name and company number, and the address of its registered office;
(c)the name and contact details of the person which made the assessment;
(d)if the person which made the assessment is a company, its registered name and company number, and the address of its registered office; and
(e)the grounds for the appeal.
(5) A notice of appeal must be—
(a)accompanied by a copy of the notice of assessment given under regulation 61(3) or (6);
(b)received by the SSRO no later than six months after the person bringing the appeal received the notice of assessment; and
(c)copied to the person which made the assessment and to the Secretary of State at the same time that it is sent to the SSRO.
(6) The Secretary of State or the person which made the assessment may, within 20 working days of receipt of the copy of the notice of appeal, make a written submission to the SSRO on any matters to which they wish the SSRO to have regard in determining the appeal.
(7) Within 40 working days of receiving the notice of appeal, the SSRO must—
(a)determine the appeal; and
(b)notify in writing its determination to—
(i)the person bringing the appeal;
(ii)the person which made the assessment; and
(iii)the Secretary of State.
63.—(1) If a sub-contractor is of the opinion—
(a)that neither the condition in regulation 58(3) nor the condition in regulation 58(4) is now met in relation to the qualifying sub-contract, and
(b)that Part 2 of the Act, and these Regulations, should therefore cease to apply to that qualifying sub-contract,
it may give the SSRO notice to that effect.
(2) A notice under paragraph (1) must—
(a)be received by the SSRO no later than the contract completion date of the qualifying sub-contract;
(b)be in writing;
(c)state the date at which the sub-contractor believes that neither the condition in regulation 58(3) nor the condition in regulation 58(4) were met in relation to the qualifying sub-contract;
(d)explain the sub-contractor's reasons for that view; and
(e)be copied to the other party to the qualifying sub-contract and the Secretary of State at the same time that it is sent to the SSRO.
(3) The other party to the qualifying sub-contract or the Secretary of State may, within ten working days of receiving a copy of the notice, advise the SSRO in writing of any matters to which they consider the SSRO should have regard in deciding whether to overrule the notice.
(4) The SSRO must consider the notice and any matters to which the other party to the qualifying sub-contract or the Secretary of State have advised that it should have regard.
(5) If the SSRO does not agree that neither the condition in regulation 58(3) nor the condition in regulation 58(4) is met, it must overrule the notice.
(6) If the SSRO agrees that neither the condition in regulation 58(3) nor the condition in regulation 58(4) is met, it must—
(a)confirm the date on which neither the condition in regulation 58(3) nor the condition in regulation 58(4) were met in relation to the qualifying sub-contract; and
(b)confirm that Part 2 of the Act, and these Regulations, no longer apply to that qualifying sub-contract.
(7) The SSRO must—
(a)notify the sub-contractor, the other party to the qualifying sub-contract and the Secretary of State in writing of its decision;
(b)if the effect of the fact that Part 2 of the Act and these Regulations have ceased to apply to the qualifying sub-contract is that any other contract may also cease to be a qualifying sub-contract, notify the parties to that other qualifying sub-contract in writing of its decision.
64.—(1) In their application to qualifying sub-contracts (and to sub-contractors) by virtue of section 30(1), the following provisions of Part 2 of the Act are modified as described in this regulation.
(2) Section 16(2)(a) has effect as if for “between the Secretary of State, or an authorised person, and the primary contractor” there were substituted “ between the contracting authority and the sub-contractor ”.
(3) Section 16(2)(b) has effect as if for “or the primary contractor” there were substituted “ ,the contracting authority or the sub-contractor ”.
(4) Section 17(4)(a) has effect as if for “by the Secretary of State, or an authorised person, and the primary contractor” there were substituted “ by the contracting authority and the sub-contractor ”.
(5) Section 18(1) has effect as if for “The Secretary of State or an authorised person, and the primary contractor” there were substituted “ The contracting authority and the sub-contractor ”.
[F10(5A) Section 21(1) has effect as if for “the Secretary of State” there were substituted “the contracting authority”]
(6) Section 21(5) (direction excluding final price adjustment) does not apply.
(7) Section 35(1) has effect as if—
(a)the contracting authority (in the case of a qualifying sub-contract), and
(b)the person who proposes to enter into the qualifying sub-contract,
were persons mentioned in section 35(2).
(8) Section 35(3)(b) has effect as if for “other proposed party to the contract” there were substituted “ proposed sub-contractor ”;
(9) Section 35(4)(a) has effect as if for “by one party to the contract to the other” there were substituted “ by the sub-contractor to the Secretary of State, or by the Secretary of State to the sub-contractor ”;
(10) Section 35(4)(b) has effect as if for that subsection there were substituted—
“(b)in the case of a proposed qualifying sub-contract—
(i)by the proposed sub-contractor to the Secretary of State; or
(ii)by the Secretary of State to the proposed sub-contractor.”
(11) Section 43(1) has effect as if after the definition of “authorised person” there were inserted—
“contracting authority” means the party which is, or would be, liable to pay the contract price under a qualifying sub-contract.”
Textual Amendments
F10Reg. 64(5A) inserted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 20
65.—(1) In their application to qualifying sub-contracts (and to sub-contractors) by virtue of section 30(1), these Regulations are modified as described in this regulation.
(2) Regulation 2(1) has effect as if after the definition of “contract completion date” there were inserted—
“contracting authority” means the party which is, or would be, liable to pay the contract price under a qualifying sub-contract.”
(3) Part 2 (qualifying defence contracts) does not apply.
(4) Regulation 11 (steps in determining profit rate) has effect as if—
(a)in paragraph (6), for each “Secretary of State” there were substituted “ contracting authority ”;
(b)in paragraph (8), for “Secretary of State” there were substituted “ contracting authority ”.
(5) Regulation 12 (calculation of POCO) has effect as if in paragraphs (2) and (3) for “Secretary of State” there were substituted “ contracting authority ”.
(6) Regulation 13 (rates agreed on a group basis) does not apply.
F11(7) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(8) Regulation 16 (final price adjustment) has effect as if—
(a)in paragraph (1)—
(i)for “£5,000,000” there were substituted “ £50,000,000 ”;
[F12(ii)for the words “an adjustment” to “(“final price adjustment”)” there were substituted “a payment of a specified amount (“a final price adjustment”) may be made to or by the Secretary of State”;]
(b)paragraphs (2) and (3) were omitted.
(9) Regulation 18 (determination of contract profit rate adjustments) has effect as if—
(a)in paragraph (1), the words “(including an adjustment agreed on a group basis under regulation 13)” were omitted;
(b)in paragraph (5), for the words “the contract price is to be adjusted by a specified amount” there were substituted “ a payment of a specified amount must be made to or by the Secretary of State ”.
[F13(9A) Regulation 20(7)(a) has effect as if after the words “contract completion date” there were inserted “or the date on which it is determined that the contract is no longer a qualifying sub-contract”.]
(10) In regulation 22 (general requirements and interpretation), sub-paragraphs (2)(a)(iii) and (2)(e) do not apply.
(11) Regulation 23 (contract pricing statement) has effect as if in sub-paragraph (2)(e)(ii) for “by the Secretary of State” there were substituted “ by either the contracting authority or the Secretary of State ”.
(12) In regulation 25 (contract notification report), sub-paragraphs (2)(g) to (i) do not apply.
(13) In regulation 27 (interim contract report), sub-paragraphs (4)(j) to (l) do not apply.
(14) In regulation 28 (contract completion report), sub-paragraphs 2(l) to (n) do not apply.
[F14(15) Regulation 52 has effect as if—
(a)in paragraph (2)(a) for “qualifying defence contract by virtue of section 14(3)”, there were substituted “qualifying sub-contract”;
(b)paragraph (2)(b) were omitted.]
[F15(16) The Schedule (re-determination of contract price) has effect as if, in the definition of “the parties”, for “Secretary of State” there were substituted “contracting authority”.]
Textual Amendments
F11Reg. 65(7) omitted (1.4.2019) by virtue of The Single Source Contract (Amendment) (No. 2) Regulations 2018 (S.I. 2018/1350), regs. 1(3), 12(a)
F12Reg. 65(8)(a)(ii) substituted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 21(2)
F13Reg. 65(9A) inserted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 21(3)
F14Reg. 65(15) inserted (31.1.2019) by The Single Source Contract (Amendment) (No. 2) Regulations 2018 (S.I. 2018/1350), regs. 1(2), 5
F15Reg. 65(16) inserted (1.4.2019) by The Single Source Contract (Amendment) (No. 2) Regulations 2018 (S.I. 2018/1350), regs. 1(3), 12(b)
66. Where the amount of an adjustment to the contract price of a qualifying sub-contract is determined by the SSRO under regulation 16(7) or calculated under regulation 17—
(a)the contract price is not to be adjusted by that amount; and
(b)a payment for that amount must be made by the Secretary of State to the sub-contractor or by the sub-contractor to the Secretary of State (whichever is appropriate).]
Textual Amendments
F16Reg. 66 inserted (1.9.2019) by The Single Source Contract (Amendment) Regulations 2019 (S.I. 2019/1106), regs. 1, 22
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: