Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
10.—(1) The price payable under a qualifying defence contract to the primary contractor must be determined in accordance with the formula—
where—
“CPR” is the contract profit rate for the contract, determined in accordance with regulation 11; and
“AC” means the primary contractor's allowable costs (see section 20), determined in accordance with one of the six regulated pricing methods described in paragraphs (4) to (11) below.
(2) The parties to a qualifying defence contract may agree which of the regulated pricing methods is to be used for that qualifying defence contract.
(3) The parties to a qualifying defence contract may agree that different regulated pricing methods are to be used for defined components of that contract.
(4) Under the firm pricing method, the allowable costs are the allowable costs as estimated at the time of agreement.
(5) Under the fixed pricing method, the allowable costs are the allowable costs as—
(a)estimated at the time of agreement; and
(b)adjusted in accordance with changes in specified indices or rates between the time of agreement and a specified time (and different times, indices or rates may be specified in relation to different allowable costs).
(6) Under the cost-plus pricing method, the allowable costs are the actual allowable costs determined during the contract or after the contract completion date.
(7) Under the estimate-based fee pricing method, the allowable costs by which the CPR is multiplied are the allowable costs as estimated at the time of agreement.
(8) The allowable costs which are added to the product of the CPR and the allowable costs determined in accordance with paragraph (7) are the actual allowable costs determined during the contract or after the contract completion date.
(9) Under the volume-driven pricing method, the allowable costs are the allowable costs per unit of volume multiplied by the actual volume of output of the contract.
(10) The allowable costs—
(a)must be estimated at the time of agreement; and
(b)may be adjusted in accordance with changes in specified indices or rates between the time of agreement and a specified time (and different times, indices or rates may be specified in relation to different allowable costs).
(11) Under the target pricing method, the allowable costs are the allowable costs as estimated at the time of agreement.
(12) In this regulation, “specified” means specified in the contract at the time of agreement.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: