- Latest available (Revised)
- Point in Time (31/01/2019)
- Original (As made)
Version Superseded: 01/04/2024
Point in time view as at 31/01/2019. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
There are currently no known outstanding effects for the The Single Source Contract Regulations 2014, Section 30.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
30.—(1) Within one month of the initial reporting date of the qualifying defence contract, the Secretary of State may by written direction require the primary contractor to provide the information described in regulation 29(2) (contract costs statement) for one or more specified periods, each such period ending on a date before the contract completion date.
(2) The contractor must provide the information required under paragraph (1) within 12 months after the last day of each period specified in the written direction.
(3) Before the contract completion date, the Secretary of State may by written direction require the primary contractor to provide the information described in any of—
(a)regulation 23(2) (contract pricing statement);
(b)regulation 24(2) (contract reporting plan);
(c)regulation 27(4) and (5) (interim contract report);
(d)regulation 29(2) (contract costs statement).
(4) The Secretary of State may make more than one written direction under paragraph (3) in relation to the contract.
(5) The contractor must provide the information required under paragraph (3)(a) or (b)—
(a)if the contractor and the Secretary of State agree a date which is no more than three months after the date of receiving the written direction, by that date; or
(b)if no such agreement is made, within one month of receiving the written direction.
(6) The contractor must provide the information required under paragraph (3)(c)—
(a)if the contractor and the Secretary of State agree a date which is no more than six months after the date of receiving the written direction, by that date; or
(b)if no such agreement is made, within two months after receiving the written direction.
(7) The contractor must provide the information required under paragraph (3)(d)—
(a)if the contractor and the Secretary of State agree a date which is no more than 18 months after the date of receiving the written direction, by that date; or
(b)if no such agreement is made, within six months after receiving the written direction.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: