There are currently no known outstanding effects for the The Single Source Contract Regulations 2014, Section 39.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
39.—(1) The Secretary of State may, for any relevant financial year, by written notice require the designated person to provide a rates comparison report for any one or more pricing QBU for that relevant financial year.
(2) The designated person must provide a rates comparison report within two months after receiving a notice under paragraph (1).
(3) The Secretary of State may only require one rates comparison report for any one QBU in a relevant financial year.
(4) The report must contain the following information—
(a)a list of all qualifying defence contracts and qualifying sub-contracts—
(i)that have a contract completion date on or after the first day of the relevant accounting period;
(ii)to which the designated person or any person associated with it is party; and
(iii)the price of which have been or will be calculated using a cost recovery rate which relates to the costs of the QBU;
(b)for each of those contracts—
(i)any unique identifying number allocated to the contract by the contractor;
(ii)any unique identifying number allocated to the contract by the Secretary of State;
(iii)any title given in the contract;
(iv)the date on which the contract was entered into;
(v)the [F1contract] pricing method or methods used in determining the price payable under the contract; and
(vi)whether the contract is a qualifying defence contract or a qualifying sub-contract;
(c)a list of all the cost recovery rates used in any of those contracts, and the actual value of each of those rates as provided in the QBU actual cost analysis report; and
(d)for each cost recovery rate used in determining the contract price under regulation 10 (or, if the price has been re-determined [F2in accordance with the Schedule], used in the most recent determination)—
(i)the actual amount of the cost recovery base attributable to the contract;
(ii)the amount of the cost recovery base used in determining the contract price; and
(iii)the cost recovery rate used in determining the contract price.
Textual Amendments
F1Word in reg. 39(4)(b)(v) substituted (1.4.2024) by The Single Source Contract (Amendment) Regulations 2024 (S.I. 2024/420), regs. 1(2), 38
F2Words in reg. 39(4)(d) substituted (1.4.2019) by The Single Source Contract (Amendment) (No. 2) Regulations 2018 (S.I. 2018/1350), regs. 1(3), 9
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: