4.—(1) A resolution plan must set out (in addition to the analysis made under paragraph 3) options for applying the resolution tools and exercising the resolution powers or taking insolvency proceedings in respect of the relevant institution.
(2) The plan must include—
(a)a summary of its key elements;
(b)a summary of any material changes to the institution, including any change to its legal or organisational structure or its business or financial position, which has occurred since the preparation of the plan or the date on which the plan was last revised;
(c)a demonstration of how the institution’s core business lines and critical functions could be separated, legally or economically, in order to secure continuity in the event of the failure of the institution;
(d)an estimation of the time required for the execution of each material element of the plan;
(e)a detailed description of the assessment of resolvability made by the Bank in accordance with Chapter 1 of Part 6;
(f)a description of any measures required by the Bank for addressing or removing impediments to resolvability in accordance with Chapter 3 of Part 6;
(g)a description of the process for determining the value and marketability of the institution’s assets, core business lines and critical functions;
(h)a detailed description of the arrangements made for ensuring that information required by the Bank for drawing up and implementing the plan is kept up to date and can be provided by the institution at any time;
(i)an explanation of how options for applying the resolution tools and exercising the resolution powers could be financed (without the assumption that the institution would be in receipt of the support or assistance referred to in paragraph 2(3));
(j)a detailed description of the different strategies that could be adopted for applying the resolution tools and exercising the resolution powers according to the different circumstances under which the institution may fail or be likely to fail and any time constraints that may be applicable;
(k)a description of factors which are critically inter-related;
(l)an description of the available options for maintaining access to payments and clearing services and other relevant infrastructure;
(m)an assessment of the portability of clients’ positions;
(n)an analysis of the impact that the implementation of the plan would have on the employees of the institution, including an assessment of costs associated with such impact;
(o)a description of procedures envisaged for consulting employees when applying the resolution tools and exercising the resolution powers, taking account of applicable arrangements for dialogue, including dialogue with trade unions and workers’ representatives;
(p)a plan for media and public communication;
(q)the minimum requirement for own funds and eligible liabilities determined in accordance with Chapter 1 of Part 9 and, where applicable, a deadline for meeting that requirement;
(r)where applicable, the minimum requirement for own funds and contractual bail-in instruments (within the meaning given in article 148(3)) and a deadline for meeting that requirement;
(s)a description of the institution’s operations and systems which are essential for the maintaining in working order its infrastructure, information technology and other operational processes; and
(t)any opinion expressed by the institution about any of these elements or any other matter included in the plan.
(3) Where appropriate and reasonably practicable, the elements of the plan set out in sub-paragraph (2) are to be quantified.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: