Search Legislation

The Public Contracts Regulations 2015

Status:

This is the original version (as it was originally made).

SUB-SECTION 2Thresholds
Threshold amounts

5.—(1) This Part applies to procurements with a value net of VAT estimated to be equal to or greater than the following thresholds:—

(a)for public works contracts, the sum specified in Article 4(a) of the Public Contracts Directive;

(b)for public supply contracts and public service contracts awarded by central government authorities, and design contests organised by such authorities, the sum specified in Article 4(b) of the Public Contracts Directive, subject to paragraph (2);

(c)for public supply contracts and public service contracts awarded by sub-central contracting authorities, and design contests organised by such authorities, the sum specified in Article 4(c) of the Public Contracts Directive;

(d)for public service contracts for social and other specific services listed in Schedule 3, the sum specified in Article 4(d) of the Public Contracts Directive.

(2) Where public supply contracts are—

(a)awarded by central government authorities operating in the field of defence, and

(b)concern products not covered by Schedule 4,

the applicable threshold for the purposes of paragraph (1) is the sum specified in Article 4(c) of the Public Contracts Directive.

(3) References in paragraphs (1) and (2) to the Public Contracts Directive are references to that Directive as amended from time to time.

(4) The value in pounds sterling of any amount expressed in euro in any of the provisions of the Public Contracts Directive mentioned in this regulation shall be taken to be the value for the time being determined by the Commission for the purpose of that provision and published from time to time in the Official Journal in accordance with Article 6 of the Public Contracts Directive.

Methods for calculating the estimated value of procurement
General rules

6.—(1) The calculation of the estimated value of a procurement shall be based on the total amount payable, net of VAT, as estimated by the contracting authority, including any form of option and any renewals of the contracts as explicitly set out in the procurement documents.

(2) Where the contracting authority provides for prizes or payments to candidates or tenderers it shall take them into account when calculating the estimated value of the procurement.

(3) Where a contracting authority is comprised of separate operational units, account shall be taken of the total estimated value for all those units.

(4) But where a separate operational unit is independently responsible for its procurement, or certain categories of its procurement, the values may be estimated at the level of the unit in question.

(5) The choice of the method used to calculate the estimated value of a procurement shall not be made with the intention of excluding it from the scope of this Part.

(6) A procurement shall not be subdivided with the effect of preventing it from falling within the scope of this Part, unless justified by objective reasons.

(7) The estimated value shall be calculated as at the moment at which the call for competition is sent or, in cases where a call for competition is not foreseen, at the moment at which the contracting authority commences the procurement procedure (for example, where appropriate, by contacting economic operators in relation to the procurement).

(8) In the case of framework agreements and dynamic purchasing systems, the value to be taken into consideration shall be the maximum estimated value, net of VAT, of all the contracts envisaged for the total term of the framework agreement or the dynamic purchasing system.

(9) In the case of innovation partnerships, the value to be taken into consideration shall be the maximum estimated value, net of VAT, of the research and development activities to take place during all stages of the envisaged partnership as well as of the supplies, services or works to be developed and procured at the end of the envisaged partnership.

(10) In the case of public works contracts, the calculation of the estimated value shall take account of both the cost of the works and the total estimated value of the supplies and services that are made available to the contractor by the contracting authority provided that they are necessary for executing the works.

Treatment of lots

(11) Where a proposed work or a proposed provision of services may result in contracts being awarded in the form of separate lots, account shall be taken of the total estimated value of all such lots.

(12) Where a proposal for the acquisition of similar supplies may result in contracts being awarded in the form of separate lots, account shall be taken of the total estimated value of all such lots when applying regulation 5(1)(b) and (c) (read with regulation 5(2)).

(13) For the purposes of paragraphs (11) and (12), where the aggregate value of the lots is equal to or greater than the relevant threshold mentioned in regulation 5, this Part applies to the awarding of each lot.

(14) Despite paragraphs (11) to (13), contracting authorities may, subject to paragraph (15), award contracts for individual lots without applying the procedures provided for by this Part, but only if the estimated value, net of VAT, of the lot concerned is less than—

(a)80,000 euro for supplies or services, or

(b)1 million euro for works.

(15) The aggregate value of the lots awarded in reliance on paragraph (14) shall not exceed 20% of the aggregate value of all the lots into which the proposed work, the proposed acquisition of similar supplies, or the proposed provision of services, has been divided.

Other specific rules

(16) In the case of public supply or service contracts which are regular in nature or which are intended to be renewed within a given period, the calculation of the estimated contract value shall be based on either of the following:—

(a)the total actual value of the successive contracts of the same type awarded during the preceding 12 months or financial year adjusted, where possible, to take account of the changes in quantity or value which would occur in the course of the 12 months following the initial contract;

(b)the total estimated value of the successive contracts awarded during the 12 months following the first delivery, or during the financial year where that is longer than 12 months.

(17) In the case of public supply contracts relating to the leasing, hire, rental or hire purchase of products, the value to be taken as a basis for calculating the estimated contract value shall be as follows:—

(a)in the case of fixed-term public contracts, where that term is less than or equal to 12 months, the total estimated value for the term of the contract or, where the term of the contract is greater than 12 months, the total value including the estimated residual value;

(b)in the case of public contracts without a fixed term, or public contracts the term of which cannot be defined, the monthly value multiplied by 48.

(18) In the case of public service contracts, the basis for calculating the estimated contract value shall, where relevant be the following:—

(a)in the case of insurance services, the premium payable and other forms of remuneration;

(b)in the case of banking and other financial services, the fees, commissions payable, interest and other forms of remuneration;

(c)in the case of design contracts, the fees, commissions payable and other forms of remuneration.

(19) In the case of public service contracts which do not indicate a total price, the basis for calculating the estimated contract value shall be the following:—

(a)in the case of fixed-term contracts where that term is less than or equal to 48 months, the total value for their full term;

(b)in the case of contracts without a fixed term or with a term greater than 48 months, the monthly value multiplied by 48.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources