You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
The Public Contracts Regulations 2015, Section 4 is up to date with all changes known to be in force on or before 30 January 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
4.—(1) In the case of mixed contracts which have as their subject-matter different types of procurement all of which are covered by this Part—
(a)contracts which have as their subject-matter two or more types of procurement (works, services or supplies) shall be awarded in accordance with the provisions applicable to the type of procurement that characterises the main subject-matter of the contract in question; and
(b)in the case of—
(i)mixed contracts consisting partly of services to which Section 7 applies and partly of other services, or
(ii)mixed contracts consisting partly of services and partly of supplies,
the main subject-matter shall be determined in accordance with which of the estimated values of the respective services, or of the respective services and supplies, is the highest.
(2) In the case of contracts which have as their subject-matter procurement covered by this Part and procurement not covered by this Part—
(a)where the different parts of a given contract are objectively separable—
(i)contracting authorities may choose to award separate contracts for the separate parts or to award a single contract;
(ii)where contracting authorities choose to award separate contracts for separate parts, the decision as to which legal regime applies to any one of such separate contracts shall be taken on the basis of the characteristics of the separate part concerned;F1...
(iii)where contracting authorities choose to award a single contract, this Part applies to the ensuing mixed contract, irrespective of—
(aa)the value of the parts that would otherwise fall under a different legal regime, and
(bb)which legal regime those parts would otherwise have been subject to;[F2; and
(iv)where, in the case of mixed contracts containing elements of public contracts covered by this Part and of concession contracts, contracting authorities choose to award a single contract, that contract shall be awarded in accordance with this Part, provided that the estimated value of the part of the contract which constitutes a public contract covered by this Part, calculated in accordance with regulation 6, is equal to or greater than the relevant threshold set out in regulation 5;]
(b)where the different parts of a given contract are objectively not separable, the applicable legal regime shall be determined on the basis of the main subject-matter of that contract.
[F3(2A) In the case of contracts which have as their subject-matter both procurement covered by this Part and procurement for the pursuit of an activity which is subject to the Utilities Contracts Regulations 2016, the applicable rules shall, despite paragraph (2), be determined by regulations 6 and 7 of those Regulations.]
(3) But where part of a given contract is covered by Article 346 of TFEU or the Defence and Security Regulations, regulation 16 applies instead of [F4paragraphs (1) to (2A)].
Textual Amendments
F1Word in reg. 4(2)(a)(ii) omitted (18.4.2016) by virtue of The Public Procurement (Amendments, Repeals and Revocations) Regulations 2016 (S.I. 2016/275), reg. 1(1), Sch. 2 para. 4(2)(a) (with reg. 5)
F2Reg. 4(2)(a)(iv) and word inserted (18.4.2016) by The Public Procurement (Amendments, Repeals and Revocations) Regulations 2016 (S.I. 2016/275), reg. 1(1), Sch. 2 para. 4(2)(b) (with reg. 5)
F3Reg. 4(2A) inserted (18.4.2016) by The Public Procurement (Amendments, Repeals and Revocations) Regulations 2016 (S.I. 2016/275), reg. 1(1), Sch. 2 para. 4(3) (with reg. 5)
F4Words in reg. 4(3) substituted (18.4.2016) by The Public Procurement (Amendments, Repeals and Revocations) Regulations 2016 (S.I. 2016/275), reg. 1(1), Sch. 2 para. 4(4) (with reg. 5)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: