93.—(1) This regulation limits the time within which proceedings may be started where the proceedings seek a declaration of ineffectiveness.
(2) Such proceedings must be started—
(a)where paragraph (3) or (5) applies, within 30 days beginning with the relevant date mentioned in that paragraph;
(b)in any event, within 6 months beginning with the day after the date on which the contract was entered into.
(3) This paragraph applies where a relevant contract award notice has been published in the Official Journal, in which case the relevant date is the day after the date on which the notice was published.
(4) For that purpose, a contract award notice is relevant if, and only if—
(a)the contract was awarded without prior publication of a contract notice; and
(b)the contract award notice includes justification of the decision of the contracting authority to award the contract without prior publication of a contract notice.
(5) This paragraph applies where the contracting authority has informed the economic operator of—
(a)the conclusion of the contract, and
(b)a summary of the relevant reasons,
in which case the relevant date is the day after the date on which the economic operator was informed of the conclusion or, if later, was informed of a summary of the relevant reasons.
(6) In paragraph (5), “the relevant reasons” means the reasons which the economic operator would have been entitled to receive in response to a request under regulation 55(2).
(7) For the purposes of this regulation, proceedings are to be regarded as started when the claim form is issued.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: