14.—(1) No part of any numbered work in Schedule 1 (authorised development) is to commence until a written scheme for the provision and implementation of pollution control relevant to the construction of that numbered work has been submitted to and, following consultation with the relevant district authorities and the Environment Agency, approved in writing by the relevant planning authority.
(2) The written scheme must include the following, which must comply with or include relevant measures or details set out in the environmental statement—
(a)details of measures for the collection, treatment and disposal of all water entering or arising on the Order land;
(b)details of measures for the collection and disposal of foul drainage; and
(c)details of measures for the storage of any chemicals, oil or fuel.
(3) The approved scheme must be implemented in full.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: