The Swansea Bay Tidal Generating Station Order 2015

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: PART 1

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Swansea Bay Tidal Generating Station Order 2015, PART 1. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 1E+WFor the protection of Associated British Ports

InterpretationE+W

1.  In this Part—

“accumulation” means any accumulation of silt or other material (including any materials used to construct the authorised development) which constitutes an impediment to navigation at or in the approaches to the harbours;

“authorised development” means the works set out in Parts 1A, 1B and 2 of Schedule 1 (authorised development, and ancillary and necessary works);

“construction” includes execution and placing, maintenance, extension, enlargement, alteration, replacement, relaying, and removal, or the carrying out of an operation, and “construct” and “constructed” are to be construed accordingly;

“erosion” means any erosion of the bed or banks of the sea or of any jetty or other structure of whatever nature within the harbours or the approaches to the harbours;

“the harbours” means the ports of Swansea and Port Talbot;

“plans” includes sections, descriptions, drawings, specifications, proposed method statements and hydraulic information;

“port land” means any land held by AB Ports for the purpose of its statutory undertaking;

“specified work” means any tidal work and any work or operation authorised by this Order on port land or which may affect port land or navigation in respect of the harbours or the functions of AB Ports in relation to the operation of the harbours; and

“tidal work” includes dredging authorised by this Order or any marine licence granted under Part 4 of the 2009 Act relating to the authorised development.

Commencement Information

I1Sch. 8 para. 1 in force at 30.6.2015, see art. 1

GeneralE+W

2.  For the protection of AB Ports in relation to the harbours the following provisions have effect unless otherwise agreed in writing between the undertaker and AB Ports.

Commencement Information

I2Sch. 8 para. 2 in force at 30.6.2015, see art. 1

Acquisition or use of port landE+W

3.—(1) The undertaker must not under the powers conferred by this Order acquire or use, or acquire new rights over, port land without the consent of AB Ports.

(2) The undertaker must not exercise powers conferred by article 15 (authority to survey and investigate the land) or the powers conferred by section 11(3) of the 1965 Act (powers of entry) in respect of any port land without the consent of AB Ports.

(3) Article 25 (power to override easements and other rights) does not apply to any rights held by AB Ports for the purpose of its statutory undertaking, except with the consent of AB Ports.

(4) The consent of AB Ports under this paragraph must not be unreasonably withheld but may be given subject to reasonable conditions.

Commencement Information

I3Sch. 8 para. 3 in force at 30.6.2015, see art. 1

Approval of plans and arrangementsE+W

4.—(1) Before commencing the construction of any specified work, the undertaker must furnish to AB Ports plans of that work for its approval.

(2) Before decommissioning the generating station comprised in the authorised development the undertaker must furnish to AB Ports for its approval proposed arrangements for the removal or retention of the authorised development and for making it safe and managing it after it has ceased to be used for the generation of electricity.

(3) Any approval of AB Ports under this paragraph—

(a)must not be unreasonably withheld;

(b)may be given subject to such reasonable requirements as AB Ports may make for the protection of the harbours and navigation within the harbours and the approaches to the harbours, including a requirement for the undertaker to carry out protective works at its own expense;

(c)may not vary the operation of this Order.

(4) The undertaker must—

(a)carry out any specified work and any protective works required under sub-paragraph (3) in accordance with the plans approved under sub-paragraph (1) or settled under article 50 (arbitration); and

(b)comply with any arrangements approved under sub-paragraph (2) or settled under article 50 (arbitration).

(5) If AB Ports fails to express its disapproval of any plans or arrangements within 56 days after they have been delivered to it under sub-paragraph (1) or (2), it is deemed to have approved them.

(6) Nothing in this paragraph affects the operation of article 42 (application of Energy Act 2004 in relation to decommissioning) or a decommissioning programme approved under that article.

Commencement Information

I4Sch. 8 para. 4 in force at 30.6.2015, see art. 1

Notice of worksE+W

5.  The undertaker must give to AB Ports not less than 56 days’ written notice of its intention to commence the construction of a specified work and, not more than 14 days after completion of such construction, must give to AB Ports written notice of such completion.

Commencement Information

I5Sch. 8 para. 5 in force at 30.6.2015, see art. 1

InspectionE+W

6.  The undertaker must at all reasonable times during construction of a specified work and thereafter allow AB Ports, its servants and agents, access to such work and all reasonable facilities for inspection of any such work subject always to the reasonable stipulations of the undertaker relating to health, safety, security and confidentiality.

Commencement Information

I6Sch. 8 para. 6 in force at 30.6.2015, see art. 1

Temporary worksE+W

7.—(1) After the purpose of any temporary works has been accomplished the undertaker must with all reasonable dispatch, or after a reasonable period of notice in writing from AB Ports requiring the undertaker so to do, remove any such temporary works or any materials relating to them which may have been placed on port land or below the level of high water within the harbours or the approaches to the harbours by or on behalf of the undertaker.

(2) If the undertaker fails to do so within a reasonable period after receiving such notice, AB Ports may remove the same and may recover the reasonable costs of doing so from the undertaker.

Commencement Information

I7Sch. 8 para. 7 in force at 30.6.2015, see art. 1

Erosion or accumulationE+W

8.—(1) If during the construction of a tidal work or after the completion of that work and wholly or partly in consequence of its construction there is caused or created an accumulation or erosion the undertaker, if so requested by AB Ports acting reasonably, shall remedy such accumulation or erosion to the extent attributable to such construction and, if it refuses or fails to do so, AB Ports may itself cause the work to be done and may recover the reasonable cost of doing so from the undertaker.

(2) For the purposes of sub-paragraph (1)

(a)in the case of an accumulation, the remedy shall be its removal; and

(b)in the case of erosion, the remedy shall be the carrying out of such reconstruction works and other protective works or measures as AB Ports reasonably requires.

(3) In the event that surveys, inspection, tests and sampling carried out pursuant to paragraph 12(1)(b) establish that such accumulation or erosion would have been caused in any event by factors other than the construction of a tidal work, the undertaker shall be liable to remedy such accumulation or erosion only to the extent that the same is attributable to such construction.

(4) Nothing in this paragraph removes the need for a marine licence under Part 4 of the 2009 Act.

Commencement Information

I8Sch. 8 para. 8 in force at 30.6.2015, see art. 1

Lighting, etc.E+W

9.  The undertaker shall pay to AB Ports the reasonable costs of such alterations to the marking and lighting of the harbours and the approaches to the harbours as may be necessary in consequence of the construction of a tidal work.

Commencement Information

I9Sch. 8 para. 9 in force at 30.6.2015, see art. 1

Abandoned or decayed worksE+W

10.—(1) If any tidal work or any other work of which the undertaker is in possession in exercise of any of the powers conferred by this Order is abandoned or falls into decay, insofar as it affects or otherwise impacts upon the operation of the harbours or navigation in the approaches to the harbours, AB Ports may by notice in writing require the undertaker to take such reasonable steps as may be specified in the notice either to repair or restore the work, or any part of it, or to remove the work and (to such extent as AB Ports reasonably requires) to restore the site to its former condition.

(2) If any tidal work is in such condition that it is, or is likely to become, a danger to or an interference with navigation, AB Ports may by notice in writing require the undertaker to take such reasonable steps as may be specified in the notice—

(a)to repair and restore the work or part of it; or

(b)if the undertaker so elects, to remove the tidal work and (to such extent as AB Ports reasonably requires) to restore the site to its former condition.

(3) If after such reasonable period as may be specified in a notice under this paragraph the undertaker has failed to begin taking steps to comply with the requirements of the notice, or after beginning has failed to make reasonably expeditious progress towards their implementation, AB Ports may carry out the works specified in the notice and any expenditure reasonably incurred by it in so doing is recoverable from the undertaker.

(4) This provision shall not apply where any work is being managed and operated in accordance with any approval given by AB Ports.

(5) In the event of a difference or dispute between the undertaker and AB Ports as to the necessity of any steps or works specified in a notice by AB Ports under this paragraph, such difference or dispute shall be determined by arbitration in accordance with article 50 (arbitration).

(6) Nothing in this paragraph affects the operation of article 42 (application of Energy Act 2004 in relation to decommissioning), or a decommissioning programme approved under that article.

Commencement Information

I10Sch. 8 para. 10 in force at 30.6.2015, see art. 1

ByelawsE+W

11.  The undertaker must consult AB Ports not less than 42 days before making any byelaw under article 47 (byelaws) and shall not make any byelaw which in the reasonable opinion of AB Ports conflicts with any byelaws made by AB Ports or with any powers exercisable by AB Ports or a harbour master of AB Ports for the regulation of navigation at the harbours or the approaches to the harbours.

Commencement Information

I11Sch. 8 para. 11 in force at 30.6.2015, see art. 1

IndemnityE+W

12.—(1) Without limiting the other provisions of this Part, the undertaker is to be responsible for, and make good to AB Ports, all losses, costs, charges, damages and expenses however caused which may reasonably be incurred by or occasioned to AB Ports by reason of or arising from or in connection with—

(a)the perusal of plans and navigation schemes and the inspection of a specified work by AB Ports or its duly authorised representative;

(b)the carrying out of surveys, inspections, tests and sampling within the harbours and the approaches to the harbours—

(i)to establish the marine conditions prevailing prior to the construction of any of the tidal works in such area of the River Tawe as AB Ports has reasonable cause to believe may subsequently be affected by any accumulation or erosion which the undertaker is liable to remedy under paragraph 8; and

(ii)where AB Ports has reasonable cause to believe that the construction of any of the tidal works is causing or has caused any such accumulation or erosion;

(c)the construction or failure of a specified work, or the undertaking by AB Ports of works or measures to prevent or remedy danger or impediment to navigation or damage to any property of AB Ports arising from such construction or failure including—

(i)any additional costs of dredging incurred by AB Ports as a result of contamination of the seabed caused by the construction of the specified work; and

(ii)any damage to the lock gates or damage from flooding caused by increased wave reflection as a result of the construction of the specified work;

(d)any act or omission of the undertaker or their servants or agents whilst engaged in the construction of a specified work.

(2) Without limiting the generality of sub-paragraph (1), the undertaker must indemnify AB Ports from and against all claims and demands arising out of, or in connection with, such construction, or failure or act or omission as is mentioned in that sub-paragraph.

(3) Nothing in this paragraph imposes any liability on the undertaker to the extent that any losses, costs, charges, damages, expenses, claims or demands referred to in sub-paragraph (1) or (2) are attributable to negligence on the part of AB Ports or of any person in its employ or of its contractors or agents.

(4) AB Ports must give to the undertaker notice in writing of any claim or demand for which the undertaker may be liable under this paragraph and no settlement or compromise of any such claim or demand may be made without the consent in writing of the undertaker.

Commencement Information

I12Sch. 8 para. 12 in force at 30.6.2015, see art. 1

13.  The fact that any work or thing has been executed or done with the consent of AB Ports and in accordance with any conditions or restrictions prescribed by AB Ports or in accordance with any plans approved or deemed to be approved by AB Ports or to its satisfaction or in accordance with any directions or award of any arbitrator or in accordance with any plans approved by the Welsh Ministers and any conditions or restrictions imposed by them, does not relieve the undertaker from any liability under the provisions of this Part.

Commencement Information

I13Sch. 8 para. 13 in force at 30.6.2015, see art. 1

14.  With the exception of any duty owed by AB Ports to the undertaker expressly provided for in the foregoing provisions of this Part, nothing in this Order is to be construed as imposing upon AB Ports, either directly or indirectly, any form of duty or liability to which AB Ports would not otherwise be subject which is enforceable by proceedings before any court.

Commencement Information

I14Sch. 8 para. 14 in force at 30.6.2015, see art. 1

Statutory functionsE+W

15.  Save to the extent expressly provided for nothing in this Order affects prejudicially any statutory or other rights, powers or privileges vested in, or enjoyed by, AB Ports at the commencement of this Order.

Commencement Information

I15Sch. 8 para. 15 in force at 30.6.2015, see art. 1

ArbitrationE+W

16.  Any difference or dispute arising under this Part shall, unless otherwise agreed in writing between the undertaker and AB Ports, be determined by arbitration in accordance with article 50 (arbitration).

Commencement Information

I16Sch. 8 para. 16 in force at 30.6.2015, see art. 1

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources