Search Legislation

The Preesall Underground Gas Storage Facility Order 2015

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Licence conditions during construction of the licensed works

38.  The licence holder shall ensure that any rock misplaced or lost below the level of mean high water springs in the course of construction of the licensed works is reported to the MMO within 48 hours and located and recovered within six weeks, unless otherwise agreed in writing with the MMO.