14.—(1) Following construction of the access from the A588 comprised in Work No. 6 of Schedule 1 (authorised development) to base course level, wheel-cleaning facilities shall be provided at a location to be agreed with the relevant planning authority in writing.
(2) Unless otherwise agreed with the relevant planning authority in writing, the wheel-cleaning facilities installed shall remain available for use, and shall be maintained in full working order, at all times during the construction phase, and be used so as to ensure that no debris from any work site is deposited by vehicle wheels upon the public highway.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: