xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 9REQUIREMENTS

Control of noise during operational phase

27.—(1) No stage of the authorised development shall commence operation until a written scheme for noise management of works comprised in that stage, including monitoring and attenuation for the use of works comprised in that stage of the authorised development, has been submitted to and approved by the relevant planning authority.

(2) The noise management scheme must be implemented as approved and maintained for the duration of use of the authorised development.