The Hirwaun Generating Station Order 2015

Development consent etc. granted by the OrderE+W+S

3.—(1) Subject to the provisions of this Order and to the requirements in Schedule 2, the undertaker is granted development consent for the authorised development in Schedule 1 to be carried out within the Order limits.

(2) Subject to paragraph (3), each numbered work must be situated in the numbered area shown on the works plans.

(3) In constructing each numbered work, the undertaker may construct numbered works within the corresponding numbered areas shown on the works plans up to the limits of deviation.

Commencement Information

I1Art. 3 in force at 14.8.2015, see art. 1