The Hirwaun Generating Station Order 2015

Archaeology

11.—(1) Each of numbered works 1 and 2 of the authorised development is not to commence until a written scheme of investigation covering that numbered work has been submitted to and approved by the relevant planning authority.

(2) The written scheme of investigation is to be a technical document that outlines the aim and objectives and methods to be employed during a scheme of archaeological investigation work.

(3) The scheme must identify areas where field work or a watching brief are required, and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found.

(4) Any archaeological works or watching brief carried out under the scheme must be by a suitably qualified person or body approved by the relevant planning authority.

(5) Any archaeological works or watching brief must be carried out in accordance with the approved scheme.