INFRASTRUCTURE PLANNING
This Order grants development consent for 2 offshore wind turbine electricity generating stations in the North Sea between 125 kilometres and 290 kilometres off the United Kingdom coast together with associated development. The Order authorises the compulsory purchase of land and rights in land and the right to use land and to override easements and other rights.
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 3(1)(b)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2020
art. 4(2)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 41(A1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2020
art. 4(3)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
art. 12A
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 4(g)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 13(6)(a)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 9(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 13(6)(b)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 9(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 14
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 10(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 14
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 10(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 15(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 11(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 15(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 11(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 15(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 11(a)(iii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 15(1A)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 11(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 15(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 11(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 16(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 12(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 16(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 12(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 16(1)(a)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 12(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 16(1)(b)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 12(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 16(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 12(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 16(3)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 12(d)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 16(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 12(e)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 16(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 12(e)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 18(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 13(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 18(2)-(9)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 13(b)(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 19(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 14(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 19
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 14(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 19(2)-(5)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 14(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 20(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 15(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 20(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 15(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 20(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 15(a)(iii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 20(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 15(a)(iv)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 20(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 15(a)(v)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 20(3)
(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 15(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 21(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 16(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 21(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 16(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 21(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 16(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 22(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 17
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 23(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 18(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 23(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 18(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 23(4A)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 18(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 23(6)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 18(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 24(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 19
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 25(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 20(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 25(3)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 20(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 25(5)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 20(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 26(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 21(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 26(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 21(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 26(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 21(c)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 26(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 21(c)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 26(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 21(c)(iii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 26(5)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 21(d)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 26(6)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 21(e)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 27(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 22(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 27(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 22(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 27(3)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 22(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 28(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 23(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 28(3)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 23(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 31(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 24(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 31(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 24(b)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 31(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 24(b)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 31(3)
(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 24(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 32(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 25(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 32(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 25(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 32(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 25(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 32(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 25(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 34(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 26(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 34(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 26(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 34(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 26(a)(iii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 34(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 26(b)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 34(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 26(b)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 34(2A)
(2B)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 26(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 34(4)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 26(d)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 35(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 27(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 35(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 27(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 35(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 27(a)(iii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 35(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 27(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 35(3)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 27(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 35(5)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 27(d)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 37(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 28(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 37(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 28(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 37(1A)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 28(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 37(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 28(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 37(3)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 28(d)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 38(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 29(a)(i)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 38(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 29(a)(ii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 38(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 29(a)(iii)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 38(1A)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 29(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 38(2)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 29(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 38(3)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020
art. 29(d)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 3(1A)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2019
art. 5(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 5(7A)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2019
art. 5(e)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 5(8A)
(8B)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2019
art. 5(g)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 8A
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2019
art. 5(h)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 41
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2019
art. 5(i)
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 5(8B)(b)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021
art. 5(a)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 6(1)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021
art. 5(b)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 6A
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021
art. 5(c)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 9(3)(b)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021
art. 5(d)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 13(6)(b)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021
art. 5(e)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 14
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021
art. 5(f)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 14
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021
art. 5(f)
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 1 Pt. 3
para. 6(2)(b)
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2021
art. 4
art. 1
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
Sch. 12 Pt. 3
para. 2
The Communications Act 2003 and the Digital Economy Act 2017 (Consequential Amendments to Secondary Legislation) Regulations 2017
Sch. 4
para. 53(2)(b)
reg. 1(1)
PART 1Preliminary
Citation and commencement1
This Order may be cited as the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 and comes into force on 26th August 2015.