Search Legislation

The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Bizco 2 and Bizo 3 may enter on certain land for purposes of construction

10.—(1) For the purpose of constructing Work Nos. 2A, 3A, 4A, 5A, 6A and 8A, Bizco 2 may enter on the land shown on the works plans within the Order limits for Work Nos. 2B, 3B, 4B, 5B, 6B and 8B that has been acquired for the purpose of Project B.

(2) For the purpose of constructing Work Nos. 2B, 3B, 4B, 5B, 6B and 8B, Bizco 3 may enter on the land shown on the works plans within the Order limits for Work Nos. 2A, 3A, 4A, 5A, 6A and 8A that has been acquired for the purpose of Project A.

(3) For the purpose of constructing Work Nos. 2T, 7, 7L, 8S, 9, 10A, 10B, 10C, 10D, 10E, 10F, 10G, 10H, 10I, 10J and 10K, Bizco 2 (in common with Bizco 3), and Bizco 3 (in common with Bizco 2), may enter on the land required for those works.

Back to top

Options/Help