SCHEDULE 8Marine Licence 1: Project A Offshore Generation – Work Nos. 1A and 2T

PART 2Conditions

Progress of authorised scheme32

The undertaker must keep Trinity House, the MCA and the MMO informed of progress of the authorised scheme including—

a

notice of commencement of construction of the authorised scheme within 24 hours of commencement having occurred;

b

notice within 24 hours of any aids to navigation being established by the undertaker; and

c

notice within 5 working days of completion of construction of the authorised scheme.