23.—(1) The authorised development must not commence until a written programme for the monitoring and control of noise during the construction of the authorised development has been submitted to and, after consultation with Selby District Council, approved by the planning authority.
(2) The programme submitted and approved must specify—
(a)each location from which noise is to be monitored;
(b)the method of noise measurement;
(c)the maximum permitted levels of noise at each monitoring location during the daytime;
(d)provision as to the circumstances in which construction activities must cease as a result of a failure to comply with a maximum permitted level of noise; and
(e)the noise control measures to be employed.
(3) All activities on the Order land associated with the construction of the authorised development must be carried out in accordance with British Standards 5228-1:2009 and 5228-2:2009.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: