6.—(1) Work No. 1 must not commence until the undertaker has carried out the groundwater table level survey and the results of that survey have been submitted in writing to and, after consultation with the Environment Agency, approved by the planning authority.
(2) In subparagraph (1), “the groundwater table level survey” means a survey which—
(a)is carried out within the three existing boreholes on the Order land shown in the Geotechnical Site Investigation Report in Appendix 13A to the environmental statement or within such other boreholes on the Order land as the planning authority, after consultation with the Environment Agency, may approve,
(b)is carried out over a period of 12 months, and
(c)establishes the groundwater table level at each of those locations.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: