SCHEDULE 2REQUIREMENTS

Provision of landscaping7

1

Each part of the authorised development must not be commissioned until a written detailed landscaping scheme for that part has been submitted to and approved by the planning authority.

2

Each scheme submitted and approved must include details of all proposed hard and soft landscaping works, including—

a

the treatment of hard surfaced areas;

b

earthworks, including the proposed levels and contours of landscaped areas;

c

the seed mix for areas of grassland;

d

tree and shrub planting, including the height, size and species and the density of distribution;

e

the management of existing and new areas of grassland and tree and shrub planting;

f

an implementation timetable for the phasing and completion of the landscaping works.

3

Each scheme submitted and approved must be in accordance with the indicative landscaping plan, the biodiversity strategy and the biodiversity enhancement and management plan.

4

In subparagraph (3), “the biodiversity enhancement and management plan” means the plan approved under requirement 17(1).