Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
65.—(1) Subject to paragraph (2), the Board must give notice in writing to the contractor terminating the contract with immediate effect where, in any case, a contractor who is an individual medical practitioner has ceased to be a general medical practitioner.
(2) Where the contractor referred to in sub-paragraph (1) has ceased to satisfy the condition specified in regulation 5(1)(a) by reason of a suspension of the type described in sub-paragraph (7), the Board is not required to give notice to the contractor under sub-paragraph (1) unless—
(a)the contractor is unable to satisfy the Board that it has in place adequate arrangements for the provision of clinical services under the contract for so long as the suspension continues; or
(b)the Board is satisfied that the circumstances of the suspension are such that if the contract is not terminated with immediate effect—
(i)the safety of the contractor's patients would be at serious risk, or
(ii)the Board would be at risk of material financial loss.
(3) Sub-paragraph (4) applies where—
(a)except in a case to which paragraph 59(4) applies, the contractor consists of two or more persons practising in partnership and the condition specified in regulation 5(1)(b) is no longer satisfied; or
(b)the contractor is a company limited by shares, and the condition specified in regulation 5(1)(c) is no longer satisfied.
(4) Where this sub-paragraph applies, the Board must—
(a)give notice in writing to the contractor terminating the contract with immediate effect; or
(b)give notice in writing to the contractor confirming that the Board is prepared to allow the contract to continue, for a period specified by the Board, in accordance with sub-paragraph (5) (“the interim period”).
(5) The period specified by the Board under sub-paragraph (4)(b) must not exceed—
(a)six months; or
(b)where the failure of the contractor to continue to satisfy the condition in regulation 5(1)(b) or 5(1)(c), is by reason of a suspension described in sub-paragraph (7), the period for which that suspension continues.
(6) The Board must, during the interim period and with the consent of the contractor, employ or supply the contractor with one or more general medical practitioners for the interim period to assist the contractor in the provision of clinical services under the contract.
(7) The suspensions described in this sub-paragraph are suspension—
(a)by a Fitness to Practise Panel under—
(i)section 35D of the Medical Act 1983 M1 (functions of a fitness to practise panel) in a health case, other than an indefinite suspension under section 35D(6) of that Act, or
(ii)section 38(1) of the Medical Act 1983 M2 (power to order immediate suspension etc. after a finding of impairment of fitness to practise); or
(b)by a Fitness to Practise Panel or an Interim Orders Panel under section 41A of the Medical Act 1983 M3 (interim orders).
(8) Before deciding which of the options in sub-paragraph (4) to pursue, the Board must, if it is reasonably practicable to do so, consult the Local Medical Committee (if any) for the area in which the contractor provides services under the contract.
(9) If the contractor does not, in accordance with sub-paragraph (6), consent to the Board employing or supplying a general medical practitioner during the interim period, the Board must give notice in writing to the contractor terminating the contract with immediate effect.
(10) If, at the end of the interim period, sub-paragraph (3)(a) or (b) continues to apply to the contractor, the Board must give notice in writing to the contractor terminating the contract with immediate effect.
(11) In this paragraph—
(a)“health case” has the meaning given in section 35E(4) of the Medical Act 1983 M4 (provisions supplementary to section 35D); and
(b)“general medical practitioner” has the meaning given in regulation 5(2).
Marginal Citations
M11983 c.54. Section 35D was substituted by S.I. 2002/3135, and was amended by section 99 of, and Schedule 7 to, the Health and Social Care Act 2008 (c.14) and by S.I. 2014/1101 and S.I. 2015/794.
M2Section 38 was substituted by S.I. 2002/3135 and was amended by S.I. 2015/794.
M3Section 41A was substituted by S.I. 2002/3135 and was amended by S.I. 2006/1914 and S.I. 2015/794.
M41983 c.54. Section 35D was substituted by S.I. 2002/3135 and was amended by section 99 of, and Schedule 7 to, the Health and Social Care Act 2008, and by S.I. 2006/1914, S.I. 2014/1101, and S.I. 2015/794.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: