PART 2The renewables obligation

Determining the total number of UK ROCs to be produced in an obligation period12

1

Having determined calculations A and B for an obligation period, the Secretary of State is to determine the total number of UK ROCs required to be produced by designated electricity suppliers (“the total obligation”) for that period in accordance with paragraphs (2) to (4).

2

Where calculation A is equal to or greater than calculation B for an obligation period, the total obligation for that period is calculation A.

3

Where calculation B is greater than calculation A for an obligation period, the total obligation for that period is calculation B.

4

References to the total obligation in F1this Part are to be construed accordingly.