The Renewables Obligation Order 2015

When electricity is to be regarded as supplied to customers in Great Britain or Northern IrelandE+W

This section has no associated Explanatory Memorandum

16.—(1) For the purposes of sections 32 to 32L of the Act (in particular, for the purposes of a ROC certifying the matters within section 32B(3) or (5)), electricity generated by a generating station which cannot be shown to have been supplied to customers in Great Britain is to be regarded as having been so supplied if and to the extent that the conditions in paragraph (2) or (3) are met.

(2) The conditions in this paragraph are that—

(a)the generating station is located in Northern Ireland;

(b)the operator of the generating station or an intermediary acting on the operator's behalf sells the electricity generated by the station through the SEM Pool;

(c)an electricity supplier purchases (directly or indirectly) from the SEM Pool an amount of electricity (the “relevant amount”) which is conveyed from a transmission or distribution system located wholly or partly in Northern Ireland to Great Britain through an interconnector;

(d)the supplier—

(i)has previously agreed with the operator to purchase from the SEM Pool the relevant amount, and

(ii)supplies the electricity so purchased to customers in Great Britain; and

(e)the relevant amount in any month, when taken together with the electricity which other electricity suppliers have agreed with the operator to purchase from the SEM Pool in that month, does not exceed the total amount of electricity which the operator sells through the SEM Pool in that month.

(3) The conditions in this paragraph are that—

(a)the generating station is located in Northern Ireland and has a declared net capacity of less than 10 megawatts;

(b)the operator of the generating station sells electricity to an electricity supplier under a contract to which the operator and supplier are parties; and

(c)the electricity conveyed to the supplier under the contract—

(i)is conveyed from a transmission or distribution system located wholly or partly in Northern Ireland to Great Britain through an interconnector, and

(ii)is supplied to customers in Great Britain.

(4) For the purposes of paragraphs (2) and (3), a generating station is to be treated as if it is located in Northern Ireland if it is neither in Northern Ireland nor on land but is connected directly to a transmission or distribution system (or the part of such a system) that is located in Northern Ireland (and to no other system or part thereof).

(5) For the purposes of sections 32 to 32L of the Act (in particular, for the purposes of a ROC certifying the matters within section 32B(4) or (6)), electricity which cannot be shown to have been supplied to customers in Northern Ireland is to be regarded as having been so supplied if it has been sold through the SEM Pool or under a contract in circumstances where, had the electricity been generated by a generating station mentioned in Article 54(1) of the Energy (Northern Ireland) Order 2003, the Northern Ireland authority would have been entitled to issue a Northern Ireland certificate in respect of it.

(6) In this article—

intermediary”, in relation to the operator of a generating station, and “SEM Pool” have the same meaning as they have in Article 34 of the Renewables Obligation Order (Northern Ireland) 2009 M1 or, where that order has been revoked, as they have in any NIRO Order for the time being in force; and

Northern Ireland” has the same meaning as in Article 54(1) of the Energy (Northern Ireland) Order 2003.

Marginal Citations

M1S.R. (NI) 2009 No 154. Article 34(11)(a) and (d) contain the definitions for “SEM Pool” and “intermediary” respectively, as renumbered by article 25(4) of the Renewables Obligation (Amendment) Order (Northern Ireland) 2013/116.