The Renewables Obligation Order 2015

Generating stations not compliant with accreditation or metering requirementsE+W

This section has no associated Explanatory Memorandum

43.—(1) ROCs are not to be issued in respect of any electricity generated by a generating station during a month in which the station—

(a)is not accredited, or

(b)any conditions to which the accreditation is subject are not met.

(2) ROCs are not to be issued in respect of any electricity generated by a generating station unless—

(a)the electricity is measured using a meter which, if used for ascertaining the quantity of electricity supplied by an authorised supplier to a customer, would be approved for the purposes of paragraph 2(1)(a) of Schedule 7 to the Act, or

(b)the Authority has agreed that estimates may be provided instead of measurements using a meter.