PART 7 E+WCases and circumstances when a ROC must not be issued

Large hydro generating stations first commissioned on or before 1st April 2002E+W

54.—(1) ROCs are not to be issued in respect of any electricity generated by a large hydro generating station if the station was first commissioned on or before 1st April 2002.

(2) In this article, “large hydro generating station” means a hydro generating station which has, or has had at any time since 1st April 2002, a declared net capacity of more than 20 megawatts.