Cases and circumstances when a ROC must not be issued: general provisionsE+W
This section has no associated Explanatory Memorandum
65.—(1) Subject to paragraph (2), where by virtue of this Part ROCs are not to be issued in respect of part of the electricity generated by a generating station and that electricity is not measured separately from the remainder of the electricity generated by the station, the operator of the station must provide the Authority with an estimate of the amount of electricity generated by the station in respect of which ROCs are not to be issued.
(2) The estimate must be produced using a methodology which—
(a)has been agreed with the Authority, and
(b)in the Authority's opinion, is unlikely to underestimate the amount of electricity in respect of which ROCs are not to be issued.