4.—(1) The Agency must establish and maintain a register which contains the information referred to in Schedule 1.

(2) The Agency must enter on the register within 10 working days of receipt—

(a)the information which it receives from the Secretary of State under regulation 3(1); and

(b)any variation to that information which it receives from the Secretary of State under regulation 3(2).

(3) The Agency must maintain the register in electronic form.

(4) The Agency must ensure that the register is clearly displayed on the internet.