xmlns:atom="http://www.w3.org/2005/Atom"
  1. Introductory Text

  2. 1.Citation and commencement

  3. 2.Interpretation

  4. 3.Development consent etc. granted by the Order

  5. 4.Maintenance of authorised development

  6. 5.Limits of Deviation

  7. 6.Benefit of Order

  8. 7.Consent to transfer benefit of Order

  9. 8.Defence to proceedings in respect of statutory nuisance

  10. 9.Street works

  11. 10.Stopping up of streets

  12. 11.Public rights of way

  13. 12.Temporary prohibition or restriction of use of streets

  14. 13.Power to alter layout etc. of streets

  15. 14.Construction and maintenance of new or altered streets

  16. 15.Classification of roads

  17. 16.Access to works

  18. 17.Agreements with street authorities

  19. 18.Discharge of water

  20. 19.Authority to survey and investigate the land

  21. 20.Compulsory acquisition of land

  22. 21.Compulsory acquisition of land – incorporation of the mineral code

  23. 22.Time limit for exercise of authority to acquire land compulsorily

  24. 23.Compulsory acquisition of rights and imposition of restrictive covenants

  25. 24.Private rights

  26. 25.Application of the Compulsory Purchase (Vesting Declarations) Act 1981

  27. 26.Acquisition of subsoil and air-space only

  28. 27.Acquisition of part of certain properties

  29. 28.Rights under or over streets

  30. 29.Temporary use of land for carrying out the authorised development

  31. 30.Temporary use of land for maintaining authorised development

  32. 31.Statutory undertakers

  33. 32.Apparatus and rights of statutory undertakers in stopped up streets

  34. 33.Recovery of costs of new connections

  35. 34.Felling or lopping of trees

  36. 35.Certification of plans etc.

  37. 36.Arbitration

  38. 37.Service of notices

  39. Signature

  40. SCHEDULES

    1. SCHEDULE 1

      AUTHORISED DEVELOPMENT

      1. In the County of Northumberland

    2. SCHEDULE 2

      REQUIREMENTS

      1. 1.Interpretation

      2. 2.Approvals of submitted schemes

      3. 3.The Construction Environmental Management Plan

      4. 4.Detailed design

      5. 5.External Materials

      6. 6.St. Leonard’s junction

      7. 7.Landscaping and biosecurity

      8. 8.Trees and hedgerows

      9. 9.Public rights of way

      10. 10.Fencing and other means of enclosure

      11. 11.Drainage and water pollution post-construction

      12. 12.Surface water drainage during construction

      13. 13.Watercourse crossings

      14. 14.Contamination

      15. 15.Oil, petrol, diesel oil, lubricant or paint is only to...

      16. 16.Archaeology

      17. 17.Construction traffic

      18. 18.Turning facilities

      19. 19.Control of noise during construction of the authorised development

      20. 20.Construction hours

      21. 21.Control of dust emissions

      22. 22.Control of artificial light emissions

      23. 23.Control of deposits on highways

      24. 24.Protected species and nature conservation during construction

      25. 25.Protected species and nature conservation post construction

      26. 26.Land maintenance

      27. 27.Site compounds

      28. 28.Demolition of Rose Cottage

      29. 29.Road safety audit and monitoring

    3. SCHEDULE 3

      STREETS SUBJECT TO STREET WORKS

    4. SCHEDULE 4

      STREETS AND PRIVATE ACCESSES TO BE STOPPED UP

      1. PART 1 STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

      2. PART 2 PRIVATE ACCESSES FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

      3. PART 3 PRIVATE ACCESSES FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED

    5. SCHEDULE 5

      VARIATION OF PUBLIC RIGHTS OF WAY

      1. PART 1 SECTIONS OF PUBLIC PATH STOPPED UP

        1. 1.The section of Public Footpath No. 21 (Parish of Mitford)...

        2. 2.The section of Public Footpath No. 13 (Parish of Mitford)...

        3. 3.The section of Public Footpath No. 9 (Parish of Hebron)...

      2. PART 2 SECTIONS OF PUBLIC PATH CREATED

        1. 1.A new section of Public Footpath No. 13 (Parish of...

        2. 2.A new section of Public Footpath No. 9 (Parish of...

        3. 3.A new section of Public Footpath No. 9 (Parish of...

    6. SCHEDULE 6

      TEMPORARY PROHIBITION OR RESTRICTION OF USE OF STREETS

    7. SCHEDULE 7

      STREETS SUBJECT TO ALTERATION OF LAYOUT

      1. PART 1 STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT

      2. PART 2 STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT

    8. SCHEDULE 8

      ACCESS TO WORKS

      1. PART 1 PUBLIC ACCESS TO WORKS

      2. PART 2 PRIVATE ACCESS TO WORKS

    9. SCHEDULE 9

      LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

    10. SCHEDULE 10

      LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED

    11. SCHEDULE 11

      MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF RESTRICTIVE COVENANTS

      1. Compensation enactments

        1. 1.The enactments for the time being in force with respect...

        2. 2.(1) Without limitation on the scope of paragraph 1, the...

      2. Application of the 1965 Act

        1. 3.(1) The 1965 Act has effect with the modifications necessary...

        2. 4.For section 7 of the 1965 Act (measure of compensation)...

        3. 5.For section 8 of the 1965 Act (provisions as to...

        4. 6.The following provisions of the 1965 Act (which state the...

        5. 7.Section 11 of the 1965 Act (powers of entry) is...

        6. 8.Section 20 of the 1965 Act (protection for interests of...

        7. 9.Section 22 of the 1965 Act (interests omitted from purchase)...

  41. Explanatory Note