There are currently no known outstanding effects for the The Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015, Section 15.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
15.—(1) The operator of a production installation which is to be established in external waters must—
(a)prepare a design notification containing, subject to paragraph (6), the particulars specified in Schedule 5; and
(b)send the design notification to the competent authority.
(2) The duties in paragraph (1) must be completed at such time before the submission of a field development plan to the Department of Energy and Climate Change as will enable the operator to take account—
(a)in the design, and
(b)in the safety case prepared pursuant to regulation 17,
of any matters raised by the competent authority within three months (or such shorter period as the competent authority may specify) of that time.
(3) The operator of a production installation which is to be moved to a new location within external waters (whether from outside external waters or not) and operated there must—
(a)prepare a relocation notification containing the particulars specified in Schedule 5 not contained in any current safety case for that installation; and
(b)send the relocation notification to the competent authority
(4) The duties in paragraph (3) must be completed at such time before the submission of a field development plan to the Department of Energy and Climate Change as will enable the operator to take account of any matters raised by the competent authority within three months (or such shorter period as the competent authority may specify) of that time.
(5) The competent authority must respond to the design notification—
(a)with comments to be taken into account by the operator in the safety case; or
(b)where it has no such comments to make, with a statement to that effect.
(6) Paragraph (1) only requires the design notification to contain the particulars referred to in that paragraph to the extent that it is reasonable to expect the operator to address them at the time of sending the design notification to the competent authority.
(7) Where there is a material change in any of the particulars notified pursuant to—
(a)paragraph (1) prior to the operator sending a safety case to the competent authority in accordance with regulation 17(1)(b); or
(b)paragraph (3) prior to the operator sending—
(i)a safety case to the competent authority in accordance with regulation 17(1)(b); or
(ii)revisions to the current safety case to the competent authority in accordance with regulation 24(2),
the operator must notify the competent authority of that change as soon as practicable.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: