- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made).
B. Development by or on behalf of a sewerage undertaker consisting of—
(a)development not above ground level required in connection with the provision, improvement, maintenance or repair of a sewer, outfall pipe, sludge main or associated apparatus;
(b)the provision of a building, plant, machinery or apparatus in, on, over or under land for the purpose of survey or investigation;
(c)the maintenance, improvement or repair of works for measuring the flow in any watercourse or channel;
(d)the installation in a sewerage system of a pumping station, valve house, control panel house or switch-gear house;
(e)any works authorised by or required in connection with an order made under section 73 of the Water Resources Act 1991 (power to make ordinary and emergency drought orders)(1);
(f)any other development in, on, over or under their operational land, other than the provision of a building but including the extension or alteration of a building.
B.1 Development is not permitted by Class B if—
(a)in the case of any Class B(d) development involving the installation of a station or house exceeding 29 cubic metres in capacity, that installation is carried out at or above ground level or under a highway used by vehicular traffic;
(b)in the case of Class B(f) development, it would consist of or include the extension or alteration of a building so that—
(i)its design or external appearance would be materially affected;
(ii)the height of the original building would be exceeded, or the cubic content of the original building would be exceeded, by more than 25%; or
(iii)the floor space of the original building would be exceeded by more than 1,000 square metres; or
(c)in the case of Class B(f) development, it would consist of the installation or erection of any plant or machinery exceeding 15 metres in height or the height of anything it replaces, whichever is the greater.
B.2 Development is permitted by Class B(b) subject to the condition that, on completion of the survey or investigation, or at the expiration of 6 months from the commencement of the development concerned, whichever is the sooner, all such operations cease and all such buildings, plant, machinery and apparatus are removed and the land restored as soon as reasonably practicable to its former condition (or to any other condition which may be agreed with the local planning authority).
B.3 For the purposes of Class B—
“associated apparatus”, in relation to any sewer, main or pipe, means pumps, machinery or apparatus associated with the relevant sewer, main or pipe; and
“sludge main” means a pipe or system of pipes (together with any pumps or other machinery or apparatus associated with it) for the conveyance of the residue of water or sewage treated in a water or sewage treatment works as the case may be, including final effluent or the products of the dewatering or incineration of such residue, or partly for any of those purposes and partly for the conveyance of trade effluent or its residue.
1991 c. 57; which was amended by Schedule 22 to the Environment Act 1995 and S.I. 2013/755.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: