The Town and Country Planning (General Permitted Development) (England) Order 2015

Development not permittedE+W
This section has no associated Explanatory Memorandum

O.1  Development is not permitted by Class O if—

(a)the capacity of the system that the flue would serve exceeds 45 kilowatts thermal;

(b)the height of the flue would exceed either—

(i)the highest part of the roof by 1 metre or more, or

(ii)the height of an existing flue which is being replaced,

whichever is the highest;

(c)the installation of the flue would result in the installation on the same building of more than 1 flue forming part of either a biomass heating system or a combined heat and power system;

(d)the flue would be installed on a listed building, within the curtilage of a listed building, or on a site designated as a scheduled monument; or

(e)in the case of a building on article 2(3) land, the flue would be installed on a wall or roof slope which fronts a highway.