The Town and Country Planning (General Permitted Development) (England) Order 2015

ConditionsE+W
This section has no associated Explanatory Memorandum

K.2  Development is permitted by Class K subject to the following conditions—

(a)the development is carried out in accordance with the details in the notification referred to in paragraph K.1(b), unless the mineral planning authority have otherwise agreed in writing;

(b)no trees on the land are removed, felled, lopped or topped and no other thing is done on the land likely to harm or damage any trees, unless specified in detail in the notification referred to in paragraph K.1(b) or the mineral planning authority have otherwise agreed in writing;

(c)before any excavation other than a borehole is made, any topsoil and any subsoil is separately removed from the land to be excavated and stored separately from other excavated material and from each other;

(d)within a period of 28 days from operations ceasing, unless the mineral planning authority have agreed otherwise in writing—

(i)any structure permitted by Class K and any waste material arising from other development so permitted is removed from the land;

(ii)any borehole is adequately sealed;

(iii)any other excavation is filled with material from the site;

(iv)the surface of the land is levelled and any topsoil replaced as the uppermost layer, and

(v)the land is, so far as is practicable, restored to its condition before the development took place, including the carrying out of any necessary seeding and replanting, and

(e)the development ceases no later than a date 6 months after the elapse of the relevant period, unless the mineral planning authority have otherwise agreed in writing.