Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
10.—(1) Except where the body or person concerned has notified the hazardous substances authority that they do not wish to be consulted, the authority must, before determining an application for hazardous substances consent, consult—
(a)the COMAH competent authority;
(b)the district or London borough council or county council concerned, where that council is not also the hazardous substances authority;
(c)the parish council concerned;
(d)the fire and civil defence authority concerned, where that authority is not also the hazardous substances authority;
(e)a person to whom a licence has been granted under section 7(2) of the Gas Act 1986 (licensing of gas transporters) M1;
(f)a person to whom a licence has been granted under section 6(1)(b) and (c) of the Electricity Act 1989 (licences authorising supply, etc) M2;
(g)where the land to which the application relates is within 2 kilometres of a royal palace, park or residence, the Secretary of State;
(h)where the land to which the application relates is in an area designated as a new town, the development corporation for the new town;
(i)where the land to which the application relates is situated within 2 kilometres of—
(i)an adjacent county, county borough, district or London borough, the council for that county, county borough, district or London borough;
(ii)the area of an adjacent fire authority and civil defence authority, that authority; or
(iii)an adjacent new town, the development corporation for the new town;
(iv)the area of a Scottish local authority, that authority;
(j)where it appears to the hazardous substances authority dealing with the application that land in the area of any other hazardous substances authority may be affected, that authority;
(k)where the application relates to land in an area to which section 28(1) of the Wildlife and Countryside Act 1981 M3 applies (sites of special scientific interest) or where it appears to the hazardous substances authority dealing with the application that an area of particular natural sensitivity or interest may be affected, in England, Natural England, or in Wales, the Natural Resources Body for Wales;
(l)where the application relates to land in an area of coal working notified to the hazardous substances authority by the Coal Authority, the Coal Authority; and
(m)where the application relates to land which is used for disposal or storage of controlled waste, the waste disposal authority concerned, where that authority is not also the hazardous substances authority.
(2) The hazardous substances authority must also, before determining an application for hazardous substances consent, consult any other persons, including any non-governmental organisation promoting environmental protection, who are affected or likely to be affected by, or have an interest in, the application, and who in the authority's opinion are unlikely to become aware of the application through the notices under regulation 6.
(3) When consulting under paragraph (1) or (2) of this regulation, the hazardous substance authority must within seven days of receiving an application—
(a)notify in writing the body or person concerned that they have received an application for hazardous substances consent and inform them of the following matters:
(i)a description of the proposal and the address or location of the land to which the application relates;
(ii)where applicable, the fact that the proposal is, or is part of, a project that is subject to a national or transboundary environmental impact assessment [F1(which have the same meaning as in any provision of retained EU law which implemented the EIA Directive)];
[F2(iia)where applicable, the fact that the project to which the proposal relates is one in respect of which the Secretary of State is required to consult any state under any provision of retained EU law which implemented the EIA Directive or which is subject to consultations between member States in accordance with Article 14(3) of the Directive;]
(iii)that the hazardous substances authority (from which relevant information can be obtained) will decide whether or not to grant consent, and if to grant, will decide on what conditions to grant;
(iv)that representations (including comments or questions) may be made to the hazardous substances authority;
(v)details of how such representations should be made and the time period for making representations, which must not be less than 28 days beginning with the day after the day on which the person or body is notified that a valid application has been received by the hazardous substances authority;
(vi)an indication of the times and places where, or means by which, relevant information will be made available; and
(b)ensure that a copy of the application is available for inspection at the offices of the hazardous substances authority during the period or periods allowed for making representations.
(4) Where a hazardous substances authority is required to consult a body under—
(a)paragraph (1)(a), or
(b)paragraph (1)(k), where it appears to the authority that an area of particular natural sensitivity or interest may be affected,
the exception in paragraph (1) does not apply.
(5) In this regulation—
“area of particular natural sensitivity or interest” has the same meaning as it has for the purposes of the Directive;
“controlled waste” has the meaning given to that expression by section 75(4) of the Environmental Protection Act 1990 M4 and “waste disposal authority” is to be construed in accordance with section 30(2) M5 of that Act;
“county”, “county borough” and “district” have the same meanings as in the Local Government Act 1972; and
“Scottish local authority” means a council constituted under section 2 of the Local Government etc. (Scotland) Act 1994 M6.
Textual Amendments
F1Words in reg. 10(3)(a)(ii) substituted (31.12.2020) by The Planning (Hazardous Substances and Miscellaneous Amendments) (EU Exit) Regulations 2018 (S.I. 2018/1234), regs. 1, 9(a); 2020 c. 1, Sch. 5 para. 1(1)
F2Reg. 10(3)(a)(iia) inserted (31.12.2020) by The Planning (Hazardous Substances and Miscellaneous Amendments) (EU Exit) Regulations 2018 (S.I. 2018/1234), regs. 1, 9(b); 2020 c. 1, Sch. 5 para. 1(1)
Marginal Citations
M11986 c. 44; section 7 was substituted by section 5 of the Gas Act 1995 (c. 45) and subsection (2) was amended by sections 3(2) and 76 of, and paragraphs 1 and 4 of Part 1 of Schedule 6 to, the Utilities Act 2000 and by S.I. 2011/2704.
M21989 c. 29; section 6 was substituted by section 30 of the Utilities Act 2000 (c. 27), subsection (1)(b) was substituted by section 136(1) of the Energy Act 2004 (c. 20) and subsection (1)(c) was amended by section 197(9) of, and Part 1 of Schedule 23 to, the Energy Act 2004.
M31981 c. 69. Section 28 was substituted by paragraph 1 of Schedule 9 to the Countryside and Rights of Way Act 2000 (c. 37) and amended by section 105(1) of, and paragraph 79 of Part 1 of Schedule 11 to, the Natural Environment and Rural Communities Act 2006 (c. 16) and paragraph 2 of Part 2 of Schedule 13 to the Marine and Coastal Access Act 2009 (c. 23).
M41990 c. 43. Section 75(1) was amended by S.I. 2006/937. Section 75(2) was amended by S.I. 2011/988.
M5There are amendments to this section, none of which are relevant to these Regulations.
M61994 c.39. Section 2 was amended by paragraph 232(1) of Schedule 22 to the Environment Act 1995 (c. 25).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: