Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
23.—(1) The occupier of a holding must not store organic manure (other than slurry), or bedding contaminated with organic manure, except—
(a)in a vessel,
(b)in a covered building (including a greenhouse),
(c)on an impermeable surface, or
(d)in the case of solid manure which can be stacked in a free-standing heap and which does not drain liquid from the material, on a temporary field site.
(2) A heap of solid manure as described in paragraph (1)(d) forming a temporary field site must occupy as small a surface area as is practically required to support the mass of the heap and prevent it from collapse.
(3) A temporary field site must not be—
(a)in a field liable to flooding or becoming waterlogged,
(b)within 50 metres of a spring, well or borehole or within 10 metres of surface water or a land drain (other than a sealed impermeable pipe),
(c)located in any single position for more than 12 consecutive months,
(d)located in the same place as an earlier one constructed within the last two years, or
(e)on land having a slope of 12 degrees or more which is within 30 metres of surface water.
(4) Solid poultry manure that does not have bedding mixed into it and is stored on a temporary field site must be covered with an impermeable material.
[F124. The occupier of a relevant holding must, when separating any slurry on the holding into its solid and liquid fractions, do so mechanically or on an impermeable surface where the liquid drains into a suitable receptacle.]
Textual Amendments
F1Reg. 24 substituted (31.12.2016) by The Nitrate Pollution Prevention (Amendment) Regulations 2016 (S.I. 2016/1190), regs. 1(1), 9(4)
25.—(1) An occupier of a holding who keeps any animals specified in column 1 of Schedule 1 must provide sufficient storage—
(a)for all slurry produced on the holding during the storage period, and
(b)for all poultry manure produced in a yard or building on the holding during the storage period.
(2) The volume of the manure produced by the animals on the holding must be calculated using the figures specified for the daily manure produced by each animal in column 2 of Schedule 1.
(3) A slurry store must have the capacity to store, in addition to the manure, any rainfall, washings or other liquid that enters the vessel (either directly or indirectly) during the storage period.
(4) Storage facilities are not necessary for slurry or poultry manure that the occupier intends will be—
(a)sent off the holding, or
(b)spread in accordance with these Regulations on land that has a low run-off risk.
(5) But in a case within paragraph (4)(b), storage facilities for an additional one week’s manure must be provided as a contingency measure in the event of spreading not being possible on some dates.
(6) This regulation does not apply to a new holding until the latest date on which a closed period under regulation 20 begins in relation to that holding (regardless of whether an exception under regulation 20(4) or 21 applies).
(7) In this regulation, “storage period” means—
(a)in the case of pigs and poultry, the period that begins with 1st October and ends with the following 1st April;
(b)in any other case, the period that begins with 1st October and ends with the following 1st March.
(8) For the purposes of this regulation, land has a “low run-off risk” if it—
(a)has an average slope of less than 3 degrees,
(b)does not have land drains (other than a sealed impermeable pipe), and
(c)is at least 50 metres from a watercourse or conduit leading to a watercourse.
25A. The occupier of a new holding must record the total size of the holding, calculated in accordance with regulation 7(4).]
Textual Amendments
F2Regs. 25A, 25B inserted (31.12.2016) by The Nitrate Pollution Prevention (Amendment) Regulations 2016 (S.I. 2016/1190), regs. 1(1), 6
25B. The occupier of a new holding with livestock must calculate and record—
(a)the amount of manure that will be produced by the number of animals expected to be kept in a building or on hardstanding during the storage period (as defined by regulation 25), using the figures in Schedule 1;
(b)the amount of storage capacity (in slurry vessels and hardstanding) required to enable compliance with regulation 25, taking into account—
(i)the amount of manure intended to be exported from the holding,
(ii)the amount of manure intended to be spread on land that has a low run-off risk, and
(iii)in the case of a slurry vessel, the amount of liquids other than slurry likely to enter the vessel; and
(c)the current storage capacity of the holding.]
Textual Amendments
F2Regs. 25A, 25B inserted (31.12.2016) by The Nitrate Pollution Prevention (Amendment) Regulations 2016 (S.I. 2016/1190), regs. 1(1), 6
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: