The Knottingley Power Plant Order 2015

Restoration of land used temporarily for construction

25.—(1) Any land within the Order limits which is used temporarily for construction must be reinstated to its former condition, or such condition as the relevant planning authority may approve in writing (or which may be provided for under an approved landscaping scheme).

(2) Reinstatement works must be commenced promptly following completion of the relevant part of the authorised development, and within three months of any required approval by the relevant planning authority. The reinstatement must be implemented in accordance with any timetable included in any relevant approved landscaping scheme.