SCHEDULE 1AUTHORISED DEVELOPMENT

PART 2Requirements

Combined heat and power28

1

Prior to the operation of Work No, 1, a review of potential opportunities for the use of heat from the authorised development must be submitted to and approved by the relevant planning authority.

2

The review shall provide for the on-going monitoring and full exploration of potential opportunities to use heat from the authorised development as part of a good quality CHP scheme in accordance with the principles set out in the CHPQA Standard Issue 3, and for the provision of subsequent reviews of such opportunities as necessary.

3

Where viable opportunities for the use of heat are identified, a scheme for the provision of the necessary Plant and pipework to the boundary of the site shall be submitted to and approved by the relevant planning authority; any plant and pipework installed up to the Order limits to enable the use of heat shall be installed in accordance with the agreed details.

4

In this requirement, ‘CHPQ Standard Issued 3’refers to the document of that name prepared by the Department for Environment, Food and Rural Affairs and published in January 2009, and the reference to a ‘good quality CHP scheme ‘should be interpreted in accordance with that document.