Regulation 2(1)
(1) Regulation | (2) Prescribed Period | (3) Prescribed Sum | (4) Payment Date |
---|---|---|---|
4(2) | 10 working days | £65 | the working day on which the budget estimate should have been dispatched |
4(3) | 20 working days | £65 | the working day on which the budget estimate should have been dispatched |
5(2) | 5 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
5(3) | 15 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
6(2) | 25 working days | £65 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
6(3) | 35 working days | £135 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
6(4) | 65 working days | £200 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
7(3) | not applicable | £335 | the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete |
7(4) | not applicable | £670 | the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete |
8(2) | 7 working days | £15 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
8(3) | the agreed date | £35 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
9(2) | 7 working days | £65 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
9(3) | 10 working days | £135 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
9(4) | 15 working days | £200 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
9(5) | the agreed date | £25 for each working day after the agreed date up to and including the day on which the works at the premises are commenced | the working day on which the works at the premises are commenced |
9(6) | the agreed date | £135 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
9(7) | the agreed date | £200 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
9(8) | the agreed date | £270 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
9(9) | the agreed date | £135 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
9(10) | the agreed date | £200 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
9(11) | the agreed date | £270 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
10(2) | 2 hours | £65 | the working day after the day on which the emergency attendance should have taken place |
10(3) | 2 calendar days | £15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
10(4) | 10 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
10(5) | 20 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
10(6) | 25 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
11(2) | 25 working days | £15 for each working day after the end of the prescribed period up to and including the day the quotation is dispatched | the working day on which the quotation is dispatched |
12(2) | the agreed date | £15 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
12(3) | 35 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the works are completed | the working day on which the works are completed |
14(1) | 10 working days | £65 | not applicable |