xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

Regulation 2(1)

SCHEDULE 1E+W+SData for the Purpose of Calculating Payments

Prescribed periods and prescribed sums applicable to all electricity distributorsE+W+S

(1)

Regulation

(2)

Prescribed Period

(3)

Prescribed Sum

(4)

Payment Date

4(2)10 working days£65

the working day on which the budget estimate should have been dispatched

4(3)20 working days£65

the working day on which the budget estimate should have been dispatched

5(2)5 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
5(3)15 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
6(2)25 working days

£65 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
6(3)35 working days

£135 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
6(4)65 working days

£200 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
7(3)not applicable£335

the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete

7(4)not applicable£670

the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete

8(2)7 working days

£15 for each working day after the end of the prescribed period up to and including the day on which contact occurs

the working day on which contact occurs
8(3)the agreed date

£35 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
9(2)7 working days

£65 for each working day after the end of the prescribed period up to and including the day on which contact occurs

the working day on which contact occurs
9(3)10 working days£135 for each working day after the end of the prescribed period up to and including the day on which contact occursthe working day on which contact occurs
9(4)15 working days

£200 for each working day after the end of the prescribed period up to and including the day on which contact occurs

the working day on which contact occurs
9(5)the agreed date

£25 for each working day after the agreed date up to and including the day on which the works at the premises are commenced

the working day on which the works at the premises are commenced
9(6)the agreed date

£135 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
9(7)the agreed date

£200 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
9(8)the agreed date

£270 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
9(9)the agreed date

£135 for each working day after the agreed date up to and including the day on which energisation occurs

the working day on which energisation occurs
9(10)the agreed date

£200 for each working day after the agreed date up to and including the day on which energisation occurs

the working day on which energisation occurs
9(11)the agreed date

£270 for each working day after the agreed date up to and including the day on which energisation occurs

the working day on which energisation occurs
10(2)2 hours£65

the working day after the day on which the emergency attendance should have taken place

10(3)2 calendar days

£15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed

the working day on which the fault rectification works are completed
10(4)10 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed

the working day on which the fault rectification works are completed
10(5)20 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed

the working day on which the fault rectification works are completed
10(6)25 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed

the working day on which the fault rectification works are completed
11(2)25 working days

£15 for each working day after the end of the prescribed period up to and including the day the quotation is dispatched

the working day on which the quotation is dispatched
12(2)the agreed date

£15 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
12(3)35 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the works are completed

the working day on which the works are completed
14(1)10 working days£65not applicable